Doubtnut Promotions Sticky

The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?

A

734

B

8

C

814

D

9

Video Solution
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

    A8
    B7.5
    C8.5
    D912
  • Question 2 - Select One

    The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
    In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?

    A734
    B8
    C814
    D9
  • Question 3 - Select One

    The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
    In the above question if the order of working days be as B,C,A,B,C,A…(starting with B and followed by C and A respectively), then in how many days the work will he completed?

    A734
    B8
    C814
    D9