Doubtnut Promotions Sticky

The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

A

8

B

7.5

C

8.5

D

912

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

    A8
    B7.5
    C8.5
    D912
  • Question 1 - Select One

    A, B and C can do piece of work in 18,24 and 36 days respectively . They work alternately , first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?

    A18
    B20
    C24
    D30
  • Question 1 - Select One

    Alen and Border can do a work individually in 21 and 42 days respectively. In how many days they can complete the work, working alternatively?

    A14
    B28
    C42
    D35
  • Question 1 - Select One

    A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95
  • Question 1 - Select One

    A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

    A5
    B4
    C3
    D6
  • Question 1 - Select One

    A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

    A5
    B4
    C3
    D6
  • Question 1 - Select One

    A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

    A5
    B4
    C3
    D6
  • Question 1 - Select One

    A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2

Similar Questions