A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
165
175
80
90
The correct Answer is:A
To solve the problem, we need to determine how many men were there at the beginning, given that they were supposed to complete a job in 8 days but finished it in 12 days due to 10 men dropping out every day.
1. Understand the Work Requirement:
The total work is designed to be completed in 8 days. Let the total amount of work be represented as W. If x is the number of men initially, then the work done per day by x men is x units of work per day. Therefore, the total work can be expressed as:
W=8x
2. Calculate Work Done Over 12 Days:
Since 10 men drop out every day, we need to calculate how many men are working each day for 12 days.
- On Day 1: x men work.
- On Day 2: x−10 men work.
- On Day 3: x−20 men work.
- On Day 4: x−30 men work.
- On Day 5: x−40 men work.
- On Day 6: x−50 men work.
- On Day 7: x−60 men work.
- On Day 8: x−70 men work.
- On Day 9: x−80 men work.
- On Day 10: x−90 men work.
- On Day 11: x−100 men work.
- On Day 12: x−110 men work.
3. Set Up the Equation for Total Work Done:
The total work done over 12 days can be calculated as:
W=x+(x−10)+(x−20)+(x−30)+(x−40)+(x−50)+(x−60)+(x−70)+(x−80)+(x−90)+(x−100)+(x−110)
Simplifying this gives:
W=12x−(10+20+30+40+50+60+70+80+90+100+110)
The sum of the series 10+20+30+...+110 is an arithmetic series with 11 terms:
Sum=n2×(first term+last term)=112×(10+110)=112×120=660
Therefore, we have:
W=12x−660
4. Equate the Two Expressions for Work:
Since both expressions represent the total work W, we can set them equal to each other:
8x=12x−660
5. Solve for x:
Rearranging the equation gives:
660=12x−8x
660=4x
x=6604=165
6. Conclusion:
Therefore, the number of men at the beginning was 165.
The total work is designed to be completed in 8 days. Let the total amount of work be represented as W. If x is the number of men initially, then the work done per day by x men is x units of work per day. Therefore, the total work can be expressed as:
W=8x
Since 10 men drop out every day, we need to calculate how many men are working each day for 12 days.
- On Day 1: x men work.
- On Day 2: x−10 men work.
- On Day 3: x−20 men work.
- On Day 4: x−30 men work.
- On Day 5: x−40 men work.
- On Day 6: x−50 men work.
- On Day 7: x−60 men work.
- On Day 8: x−70 men work.
- On Day 9: x−80 men work.
- On Day 10: x−90 men work.
- On Day 11: x−100 men work.
- On Day 12: x−110 men work.
The total work done over 12 days can be calculated as:
W=x+(x−10)+(x−20)+(x−30)+(x−40)+(x−50)+(x−60)+(x−70)+(x−80)+(x−90)+(x−100)+(x−110)
Simplifying this gives:
W=12x−(10+20+30+40+50+60+70+80+90+100+110)
The sum of the series 10+20+30+...+110 is an arithmetic series with 11 terms:
Sum=n2×(first term+last term)=112×(10+110)=112×120=660
Therefore, we have:
W=12x−660
Since both expressions represent the total work W, we can set them equal to each other:
8x=12x−660
Rearranging the equation gives:
660=12x−8x
660=4x
x=6604=165
Therefore, the number of men at the beginning was 165.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
A240B140C280D150 - Question 2 - Select One
A group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
A240B140C280D150 - Question 3 - Select One
A certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?
A8B15C12D10
A certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?
View SolutionSome staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
View SolutionA certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?
View SolutionIf 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution