A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
Find the number of days in which client wanted to complete his work.
15
10
8
can't be determined
The correct Answer is:C
Step by step video, text & image solution for A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it: Find the number of days in which client wanted to complete his work. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 1)100videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionTime taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
How many men were working on the day the project was completed as per the date of client wanted to complete it?A5B10C20Dnone of these - Question 2 - Select One
The simple interest accrued on a sum of certain principal is 1200 in 4 year at the rate of 8% per annum. What would be the simple interest accured on thrice of that principal at the rate of 6% per annum in 3 year ?
A2025B3025C2250D2150 - Question 3 - Select One
A man working 6 hours a day takes 8 days to complete a project. How many hours a day must he work to complete. It in 3 days?
A16B10C20D15
7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution