A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
How many men were working on the day the project was completed as per the date of client wanted to complete it?
A
5
B
10
C
20
D
none of these
Video Solution
Text Solution
The correct Answer is:C
|
Answer
Step by step video, text & image solution for A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it: How many men were working on the day the project was completed as per the date of client wanted to complete it? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Related Playlists
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 1)100videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Practice Problems
- Question 1 - Select One
A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
Find the number of days in which client wanted to complete his work.A15B10C8Dcan't be determined - Question 1 - Select One
The simple interest accrued on a sum of certain principal is 1200 in 4 year at the rate of 8% per annum. What would be the simple interest accured on thrice of that principal at the rate of 6% per annum in 3 year ?
A2025B3025C2250D2150 - Question 1 - Select One
A is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
A15B10C8Dcan’t be determined - Question 1 - Select One
7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
A28B21C14D7 - Question 1 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
A28B21C14D7 - Question 1 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
A60B80C20D25 - Question 1 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
A16B15C20D25 - Question 1 - Select One
A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
A15B20C25D30 - Question 1 - Select One
A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
A50B40C30D10