Doubtnut Promotions Sticky

A, B and C can alone complete a work in 15, 25 and 30 days
respectively. A and B started the work and after some days A
is replaced by C. Now the work is completed in a further of
6 4/11 days. How much of the total work did B did ?

A

411

B

415

C

512

D

511

Text Solution
Verified by Experts

The correct Answer is:(d)


Let A replaced by C after x days, so A and B worked for
X days, And the B and C for 6411=70/11 days. So
(1/15+1/25)×x+(1/25+1/30)×(70/11)=1
(8/75)×x+(7/15)=1
Solve, x=5 days
So, B worked for (5+70/11)=125/11 days
In 125/11 days, B did (125/11)×(1/25)=5/11 fo work

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • Question 2 - Select One

    A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2
  • Question 3 - Select One

    A and B can do a piece of work in 24 and 30 days respectively.
    Both started the work and worked for 6 days. Then B leaves
    the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
    alone can do the work

    A80
    B100
    C120
    D130