A, B and C can alone complete a work in 15, 25 and 30 days
respectively. A and B started the work and after some days A
is replaced by C. Now the work is completed in a further of
6 4/11 days. How much of the total work did B did ?
411
415
512
511
The correct Answer is:(d)
Let A replaced by C after x days, so A and B worked for
X days, And the B and C for 6411=70/11 days. So
(1/15+1/25)×x+(1/25+1/30)×(70/11)=1
(8/75)×x+(7/15)=1
Solve, x=5 days
So, B worked for (5+70/11)=125/11 days
In 125/11 days, B did (125/11)×(1/25)=5/11 fo work
Topper's Solved these Questions
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can complete a piece of work in 45 and 40 days respectively. Both started to work together, but after some days A left and B alone completed the rest work in 23 days. For how many days did A work?
View Solution
Knowledge Check
- Question 1 - Select One
A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?A659daysB629daysC6 daysD549days - Question 2 - Select One
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2 - Question 3 - Select One
A and B can do a piece of work in 24 and 30 days respectively.
Both started the work and worked for 6 days. Then B leaves
the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
alone can do the workA80B100C120D130
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution