Doubtnut Promotions Sticky

24 man can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How many
more days will the remaining men now take to complete the
remaining work?

A

1513

B

1645

C

1125

D

1045

Text Solution
Verified by Experts

The correct Answer is:(a)


Workman×days=Remaining workmen×days
W24×13=W20×D
20×D=24×13
D=24×1320=785=1535 days

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men can complete a piece of work in 15 days. 2 days after
    the 24 men started working, 4 men left the work. How
    many more days will the remaining men now take to
    complete the remaining work?

    A1535
    B1645
    C1125
    D1045
  • Question 2 - Select One

    45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?

    A6 days
    B8 days
    C623 days
    D734 days
  • Question 3 - Select One or More

    12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

    A10 days
    B12 days
    C15 days
    D9 days