A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?
20 men
25 men
30 men
40 men
The correct Answer is:(c)
To solve the problem, we will follow these steps:
Step 1: Determine the total work in terms of man-days.
The contractor has 60 days to complete the work with 30 men. Therefore, the total work (W) can be calculated as:
W=Number of men×Number of days=30 men×60 days=1800 man-days
Step 2: Calculate the work completed in the first 30 days.
After 30 days, it is found that only one-third of the work is completed. Thus, the work completed (W_completed) is:
Wcompleted=13W=13×1800=600 man-days
Step 3: Determine the remaining work.
The remaining work (W_remaining) after 30 days is:
Wremaining=W−Wcompleted=1800−600=1200 man-days
Step 4: Calculate the remaining time to complete the work.
Since 30 days have already passed, the remaining time (T_remaining) is:
Tremaining=60−30=30 days
Step 5: Determine the number of men needed to complete the remaining work on time.
To find the number of men (M_needed) required to complete the remaining work in the remaining time, we can use the formula:
Mneeded=WremainingTremaining=1200 man-days30 days=40 men
Step 6: Calculate the extra men needed.
The contractor originally employed 30 men, so the extra men (E) needed are:
E=Mneeded−Original men=40−30=10 men
Conclusion:
The contractor needs to employ 10 extra men to complete the work on time.
---
The contractor has 60 days to complete the work with 30 men. Therefore, the total work (W) can be calculated as:
W=Number of men×Number of days=30 men×60 days=1800 man-days
After 30 days, it is found that only one-third of the work is completed. Thus, the work completed (W_completed) is:
Wcompleted=13W=13×1800=600 man-days
The remaining work (W_remaining) after 30 days is:
Wremaining=W−Wcompleted=1800−600=1200 man-days
Since 30 days have already passed, the remaining time (T_remaining) is:
Tremaining=60−30=30 days
To find the number of men (M_needed) required to complete the remaining work in the remaining time, we can use the formula:
Mneeded=WremainingTremaining=1200 man-days30 days=40 men
The contractor originally employed 30 men, so the extra men (E) needed are:
E=Mneeded−Original men=40−30=10 men
The contractor needs to employ 10 extra men to complete the work on time.
Topper's Solved these Questions
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A70B75C80D85 - Question 2 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A100B60C75DNone of these - Question 3 - Select One
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
A20B30C15D45
A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution