Doubtnut Promotions Sticky

A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?

A

20 men

B

25 men

C

30 men

D

40 men

Video Solution
Text Solution
Verified by Experts

The correct Answer is:(c)


Let total work is w and it is given that one-third od the
work is completed after 30 days. Means
M×D=30×30=W3, so total work =30×30×3
2700=30×30+(30+p)×30, so we get
P= 30 (p=additional men)

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A70
    B75
    C80
    D85
  • Question 2 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A100
    B60
    C75
    DNone of these
  • Question 3 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45