Doubtnut Promotions Sticky

A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?

A

20 men

B

25 men

C

30 men

D

40 men

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(c)


To solve the problem, we will follow these steps:

Step 1: Determine the total work in terms of man-days.
The contractor has 60 days to complete the work with 30 men. Therefore, the total work (W) can be calculated as:
W=Number of men×Number of days=30 men×60 days=1800 man-days

Step 2: Calculate the work completed in the first 30 days.
After 30 days, it is found that only one-third of the work is completed. Thus, the work completed (W_completed) is:
Wcompleted=13W=13×1800=600 man-days

Step 3: Determine the remaining work.
The remaining work (W_remaining) after 30 days is:
Wremaining=WWcompleted=1800600=1200 man-days

Step 4: Calculate the remaining time to complete the work.
Since 30 days have already passed, the remaining time (T_remaining) is:
Tremaining=6030=30 days

Step 5: Determine the number of men needed to complete the remaining work on time.
To find the number of men (M_needed) required to complete the remaining work in the remaining time, we can use the formula:
Mneeded=WremainingTremaining=1200 man-days30 days=40 men

Step 6: Calculate the extra men needed.
The contractor originally employed 30 men, so the extra men (E) needed are:
E=MneededOriginal men=4030=10 men

Conclusion:
The contractor needs to employ 10 extra men to complete the work on time.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A70
    B75
    C80
    D85
  • Question 2 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A100
    B60
    C75
    DNone of these
  • Question 3 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45