A and C can finish a work in 40 days. They worked at it for 10 days and then A left. The remaining work is done by C alone in 30 more days. How long will it take C to finish the work alone?
30 days
22 days
40 days
25 days
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the combined work rate of A and C
A and C can finish the work together in 40 days. This means their combined work rate is:
Work rate of A + C=1 unit of work40 days=140 units per day
Hint: Remember that the work rate is calculated as the total work done divided by the time taken.
Step 2: Calculate the work done by A and C in 10 days
In 10 days, A and C will complete:
Work done in 10 days=Work rate×Time=140×10=1040=14 units
Hint: Multiply the work rate by the number of days to find the total work completed.
Step 3: Determine the remaining work
Since they completed 14 of the work, the remaining work is:
Remaining work=1−14=34 units
Hint: Subtract the completed work from the total work to find out how much is left.
Step 4: Find out how long C takes to finish the remaining work
C completes the remaining 34 units of work in 30 days. Therefore, C's work rate can be calculated as:
Work rate of C=Work doneTime=3430=3120=140 units per day
Hint: Use the formula for work rate (work done divided by time) to find C's efficiency.
Step 5: Calculate how long it will take C to finish the work alone
Since C's work rate is 140 units per day, the time taken by C to complete 1 unit of work is:
Time taken by C=1 unit140 units per day=40 days
Hint: To find the time taken for one unit of work, take the reciprocal of the work rate.
Conclusion
C will take 40 days to finish the work alone.
Final Answer: 40 days
---
A and C can finish the work together in 40 days. This means their combined work rate is:
Work rate of A + C=1 unit of work40 days=140 units per day
In 10 days, A and C will complete:
Work done in 10 days=Work rate×Time=140×10=1040=14 units
Since they completed 14 of the work, the remaining work is:
Remaining work=1−14=34 units
C completes the remaining 34 units of work in 30 days. Therefore, C's work rate can be calculated as:
Work rate of C=Work doneTime=3430=3120=140 units per day
Since C's work rate is 140 units per day, the time taken by C to complete 1 unit of work is:
Time taken by C=1 unit140 units per day=40 days
C will take 40 days to finish the work alone.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ? 40 b. 50 c. 54 d. 60
View Solution
Knowledge Check
- Question 1 - Select One
P and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?
A30 daysB20 daysC60 daysD50 days - Question 2 - Select One
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 days - Question 3 - Select One
A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A60B50C40D30
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View SolutionA and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
View SolutionA and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
View SolutionA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
View Solution