X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

A

22.5 Days / दिन

B

25 Days / दिन

C

32 Days / दिन

D

30 Days / दिन

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's denote the time taken by Y to complete the work as Y days. According to the problem, X takes 10 days less than Y, so we can express the time taken by X as Y10 days.

Step 1: Set up the equation for work done
The work done by X in one day is 1Y10 and the work done by Y in one day is 1Y. When X and Y work together, their combined work done in one day is:

1Y10+1Y

Step 2: Use the information about their combined work
According to the problem, X and Y together can finish the work in 12 days. Therefore, their combined work done in one day is:

112

Step 3: Set up the equation
We can set up the equation based on the combined work:

1Y10+1Y=112

Step 4: Find a common denominator
To solve this equation, we need to find a common denominator for the left-hand side:

Y+(Y10)(Y10)Y=112

This simplifies to:

2Y10(Y10)Y=112

Step 5: Cross-multiply to eliminate the fraction
Cross-multiplying gives us:

12(2Y10)=(Y10)Y

Step 6: Expand both sides
Expanding both sides results in:

24Y120=Y210Y

Step 7: Rearrange the equation
Rearranging the equation to one side gives us:

Y234Y+120=0

Step 8: Factor the quadratic equation
Now we can factor the quadratic equation:

(Y30)(Y4)=0

Step 9: Solve for Y
Setting each factor to zero gives us:

Y30=0orY4=0

Thus, Y=30 or Y=4.

Step 10: Determine the valid solution
Since X takes 10 days less than Y, if Y=4, then X=410=6, which is not possible. Therefore, the only valid solution is:

Y=30

Final Answer
The time taken by Y to finish the work alone is 30 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
    X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

    A30 days
    B27 days
    C20 days
    D25 days
  • A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
    A एक कार्य को 4 दिन में कर सकता है और B उसे 12 दिन में कर सकता है। दोनों मिलकर उस कार्य को कितने दिन में पूरा करेंगे?

    A3 day / 3 दिन
    B4 day / 4 दिन
    C6 day / 6 दिन
    D2 day / 2 दिन
  • X and Y together can finish a piece of work in 15 days, while Y alone can finish it in 40 days. X alone can finish the work in:

    A24 days
    B26 days
    C25 days
    D23 days