X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?
22.5 Days / दिन
25 Days / दिन
32 Days / दिन
30 Days / दिन
To solve the problem step by step, let's denote the time taken by Y to complete the work as Y days. According to the problem, X takes 10 days less than Y, so we can express the time taken by X as Y−10 days.
Step 1: Set up the equation for work done
The work done by X in one day is 1Y−10 and the work done by Y in one day is 1Y. When X and Y work together, their combined work done in one day is:
1Y−10+1Y
Step 2: Use the information about their combined work
According to the problem, X and Y together can finish the work in 12 days. Therefore, their combined work done in one day is:
112
Step 3: Set up the equation
We can set up the equation based on the combined work:
1Y−10+1Y=112
Step 4: Find a common denominator
To solve this equation, we need to find a common denominator for the left-hand side:
Y+(Y−10)(Y−10)Y=112
This simplifies to:
2Y−10(Y−10)Y=112
Step 5: Cross-multiply to eliminate the fraction
Cross-multiplying gives us:
12(2Y−10)=(Y−10)Y
Step 6: Expand both sides
Expanding both sides results in:
24Y−120=Y2−10Y
Step 7: Rearrange the equation
Rearranging the equation to one side gives us:
Y2−34Y+120=0
Step 8: Factor the quadratic equation
Now we can factor the quadratic equation:
(Y−30)(Y−4)=0
Step 9: Solve for Y
Setting each factor to zero gives us:
Y−30=0orY−4=0
Thus, Y=30 or Y=4.
Step 10: Determine the valid solution
Since X takes 10 days less than Y, if Y=4, then X=4−10=−6, which is not possible. Therefore, the only valid solution is:
Y=30
Final Answer
The time taken by Y to finish the work alone is 30 days.
---
The work done by X in one day is 1Y−10 and the work done by Y in one day is 1Y. When X and Y work together, their combined work done in one day is:
According to the problem, X and Y together can finish the work in 12 days. Therefore, their combined work done in one day is:
We can set up the equation based on the combined work:
To solve this equation, we need to find a common denominator for the left-hand side:
Cross-multiplying gives us:
Expanding both sides results in:
Rearranging the equation to one side gives us:
Now we can factor the quadratic equation:
Setting each factor to zero gives us:
Since X takes 10 days less than Y, if Y=4, then X=4−10=−6, which is not possible. Therefore, the only valid solution is:
The time taken by Y to finish the work alone is 30 days.
Topper's Solved these Questions
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionA takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View Solution
Knowledge Check
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 daysA can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
A एक कार्य को 4 दिन में कर सकता है और B उसे 12 दिन में कर सकता है। दोनों मिलकर उस कार्य को कितने दिन में पूरा करेंगे?A3 day / 3 दिनB4 day / 4 दिनC6 day / 6 दिनD2 day / 2 दिनX and Y together can finish a piece of work in 15 days, while Y alone can finish it in 40 days. X alone can finish the work in:
A24 daysB26 daysC25 daysD23 days
A takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
View SolutionA is twice as good a workman as B and together they finish a piece of work in 13 days . In how many days will B alone finish the work ?
A, B से दोगुना अच्छा कार्य करने वाला है और साथ में वे 13 दिनों में एक कार्य पूरा कर लेते है। B अकेले कितने दिनों में कार्य पूरा करेगा?
View SolutionX can do a work alone in 15 days. Y can do the same work in 30 days alone. X, Y and Z together can do that work in 9 days. In how many days Z alone can do that work?
X किसी कार्य को अकेला 15 दिन में कर सकता है |Y उसी कार्य को अकेला 30 दिन में कर सकता है | X, Y तथा Z एक साथ मिलकर उस कार्य को 9 दिन में कर सकते हैं | Z उस कार्य को अकेला कितने दिन में कर सकता है?
View SolutionA and B together can do a piece work in 20 days. B and C together can do the same work in 25 days. C and A together can do the same work in 15 days. In how many days A alone can do the work?
A तथा B मिलकर किसी कार्य को 20 दिन में कर सकते हैं | B तथा C मिलकर उसी कार्य को 25 दिन में कर सकते हैं | C तथा A मिलकर उसी कार्य को 15 दिन में कर सकते हैं | A अकेला उस कार्य को कितने दिनों में कर सकता है?
View SolutionA and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is.
View Solution