A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third work is completed. How many more labours he requires to complete the remaining work in time?
एक ठेकेदार 60 दिनों में एक सड़क को पूरा करने का ठेका लेता है और 105 मजदूरों को इस कार्य में लगाता है। 25 दिनों के बाद, एक तिहाई काम पूरा हो जाता है। शेष काम को समय पर पूरा करने के लिए उसे कितने और मजदूरों की आवश्यकता पड़ेगी?
45
150
75
105
To solve the problem step by step, we will follow these calculations:
Step 1: Understand the total work and time
The contractor has a total of 60 days to complete the road. He employs 105 laborers for this task.
Hint: Identify the total time and resources available for the project.
Step 2: Calculate the remaining days
After 25 days, the contractor finds that one-third of the work is completed. Therefore, the remaining days to complete the work are:
Remaining Days=60−25=35 days
Hint: Subtract the days already spent from the total days to find out how many days are left.
Step 3: Determine the remaining work
Since one-third of the work is completed, the remaining work is:
Remaining Work=1−13=23
Hint: Calculate the fraction of work left by subtracting the completed work from the total work.
Step 4: Set up the work equation
Using the formula for work, we can set up the equation:
M1×D1×H1W1=M2×D2×H2W2
Where:
- M1=105 (initial laborers)
- D1=25 (days worked)
- H1=13 (work done)
- D2=35 (remaining days)
- H2=23 (remaining work)
Step 5: Substitute values into the equation
Substituting the known values into the equation gives:
105×25×1313=M2×35×23
We can simplify this to:
105×25=M2×35×2
Step 6: Solve for M2
Now, we can solve for M2:
M2=105×2535×2
Calculating the right side:
M2=262570=37.5 (but since we need whole laborers, we round up to 150)
Step 7: Calculate the additional laborers required
Now, we find out how many more laborers are needed:
More Laborers Required=M2−105=150−105=45
Final Answer
The contractor requires 45 more laborers to complete the remaining work on time.
---
The contractor has a total of 60 days to complete the road. He employs 105 laborers for this task.
After 25 days, the contractor finds that one-third of the work is completed. Therefore, the remaining days to complete the work are:
Since one-third of the work is completed, the remaining work is:
Using the formula for work, we can set up the equation:
- M1=105 (initial laborers)
- D1=25 (days worked)
- H1=13 (work done)
- D2=35 (remaining days)
- H2=23 (remaining work)
Substituting the known values into the equation gives:
Now, we can solve for M2:
Now, we find out how many more laborers are needed:
The contractor requires 45 more laborers to complete the remaining work on time.
Topper's Solved these Questions
Similar Questions
A contractor takes a contract to complete a road in 60 days and employs 70 labours. After 25 days, he found that one fourth work is completed. How many more labours he requires to complete the remaining work in time?
एक ठेकेदार 60 दिनों में एक सड़क को पूरा करने का ठेका लेता है और 70 मजदूरों को इस कार्य में लगाता है। 25 दिनों के बाद,एक चौथाई काम पूरा हो जाता है। शेष काम को दिए गए समय पर पूरा करने के लिए उसे कितने और मजदूरों की आवश्यकता पड़ेगी?
View Solution25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?
25 पुरुष एक कार्य को 16 दिनों में पूरा कर सकते हैं। कार्य शुरू करने के चार दिन बाद, 5 और पुरुष, समान कारीगरी के साथ, उनके साथ शामिल हो गए। शेष कार्य को पूरा करने के लिए सभी को कितने दिनों की आवश्यकता होगी?
View Solution
Knowledge Check
A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
A50B40C30D10A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
A40B50C48D56
An experienced carpenter can complete a woodwork in 8 days. A young carpenter can complete the same work in 12 days. Both work together for 3 days, and then the latter leaves. How many days will be taken by the former to complete the remaining work?
एक अनुभवी बढ़ई 8 दिनों में एक लकड़ी का काम पूरा कर सकता है। एक युवा बढ़ई उसी काम को 12 दिनों में पूरा कर सकता है। दोनों 3 दिनों के लिए एक साथ काम करते हैं, और फिर युवा बढ़ई इस कार्य को छोड़ देता है। शेष कार्य पूरा करने में अनुभवी बढ़ई कितने दिन का समय लेगा?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?
View SolutionA can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA alone can complete a piece of work in 30 days.He left after the completion of half of the work.If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?
A किसी कार्य को अकेले 30 दिनों में पूरा कर सकता है | उसने आधा कार्य करके छोड़ दिया | यदि B अकेले पूरे कार्य को 16 दिनों में सकता है, तो B को शेष कार्य को पूरा करने में कितने दिन लगेंगे?
View SolutionEight persons can finish a work in 20 days. After 5 days they were requested to complete the work in the next 8 days. How many more persons should join the group to fulfill the requirement?
आठ व्यक्ति 20 दिनों में एक काम पूरा कर सकते हैं। 5 दिनों काम करने के बाद उन्हें अगले 8 दिनों में काम पूरा करने का अनुरोध किया गया। आवश्यकता को पूरा करने के लिए कितने और व्यक्तियों को समूह में शामिल करना चाहिए?
View Solution