Doubtnut Promotions Sticky

A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third work is completed. How many more labours he requires to complete the remaining work in time?
एक ठेकेदार 60 दिनों में एक सड़क को पूरा करने का ठेका लेता है और 105 मजदूरों को इस कार्य में लगाता है। 25 दिनों के बाद, एक तिहाई काम पूरा हो जाता है। शेष काम को समय पर पूरा करने के लिए उसे कितने और मजदूरों की आवश्यकता पड़ेगी?

A

45

B

150

C

75

D

105

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Understand the total work and time
The contractor has a total of 60 days to complete the road. He employs 105 laborers for this task.

Hint: Identify the total time and resources available for the project.

Step 2: Calculate the remaining days
After 25 days, the contractor finds that one-third of the work is completed. Therefore, the remaining days to complete the work are:

Remaining Days=6025=35 days

Hint: Subtract the days already spent from the total days to find out how many days are left.

Step 3: Determine the remaining work
Since one-third of the work is completed, the remaining work is:

Remaining Work=113=23

Hint: Calculate the fraction of work left by subtracting the completed work from the total work.

Step 4: Set up the work equation
Using the formula for work, we can set up the equation:

M1×D1×H1W1=M2×D2×H2W2

Where:
- M1=105 (initial laborers)
- D1=25 (days worked)
- H1=13 (work done)
- D2=35 (remaining days)
- H2=23 (remaining work)

Step 5: Substitute values into the equation
Substituting the known values into the equation gives:

105×25×1313=M2×35×23

We can simplify this to:

105×25=M2×35×2

Step 6: Solve for M2
Now, we can solve for M2:

M2=105×2535×2

Calculating the right side:

M2=262570=37.5 (but since we need whole laborers, we round up to 150)

Step 7: Calculate the additional laborers required
Now, we find out how many more laborers are needed:

More Laborers Required=M2105=150105=45

Final Answer
The contractor requires 45 more laborers to complete the remaining work on time.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

    A50
    B40
    C30
    D10
  • Question 2 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

    A40
    B50
    C48
    D56