Doubtnut Promotions Sticky

A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?

A

10

B

7

C

8

D

15

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the total work
A can complete the work in 35 days, and B can complete the same work in 15 days. We can find a common measure of work by calculating the least common multiple (LCM) of their days to complete the work.

- LCM of 35 and 15 = 105 (This will be our total work units)

Step 2: Calculate the work done by A and B per day
Now, we can determine how much work A and B can do in one day.

- Work done by A in one day = Total work / Days taken by A = 105 / 35 = 3 units
- Work done by B in one day = Total work / Days taken by B = 105 / 15 = 7 units

Step 3: Calculate combined work done in 7 days
When A and B work together, their combined work per day is:

- Combined work per day = Work done by A + Work done by B = 3 + 7 = 10 units

Now, we calculate the total work done by both in 7 days:

- Total work done in 7 days = Combined work per day × Number of days = 10 × 7 = 70 units

Step 4: Calculate the remaining work
Now, we can find out how much work is left after A and B have worked together for 7 days.

- Remaining work = Total work - Work done in 7 days = 105 - 70 = 35 units

Step 5: Calculate 60% of the remaining work
Next, we need to find out how much work A needs to complete, which is 60% of the remaining work.

- 60% of remaining work = 60/100 × Remaining work = 60/100 × 35 = 21 units

Step 6: Calculate the time taken by A to complete 60% of the remaining work
Now, we need to find out how long it will take A to complete 21 units of work alone.

- Time taken by A = Work to be done / Work done by A per day = 21 / 3 = 7 days

Conclusion
Thus, A alone will take 7 days to complete 60% of the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A512
    B5
    C8
    D6