A can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?

A

15

B

10

C

5

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A and B
A can complete the work in 35 days, and B can complete the same work in 15 days.

- Efficiency of A:
Efficiency of A=1 work35 days=135 work per day

- Efficiency of B:
Efficiency of B=1 work15 days=115 work per day

Step 2: Find the combined efficiency of A and B
To find the combined efficiency when A and B work together:
Combined Efficiency=Efficiency of A+Efficiency of B=135+115

To add these fractions, we need a common denominator. The least common multiple (LCM) of 35 and 15 is 105.

- Convert the efficiencies:
135=3105,115=7105

- Now, add them:
Combined Efficiency=3105+7105=10105=221 work per day

Step 3: Calculate the work done in 8 days
Now, we calculate how much work A and B can complete together in 8 days:
Work done in 8 days=Combined Efficiency×8=221×8=1621 work

Step 4: Calculate the remaining work
The total work is considered as 1 (or 105 units if we scale it). The remaining work after 8 days is:
Remaining Work=11621=211621=521 work

Step 5: Calculate 60% of the remaining work
Now we need to find 60% of the remaining work:
60% of Remaining Work=0.6×521=321=17 work

Step 6: Calculate the time taken by A to complete 60% of the remaining work
Now, we need to find out how many days A will take to complete 17 of the work:
Time taken by A=WorkEfficiency of A=17135=17×35=5 days

Final Answer
Thus, A alone will complete 60% of the remaining work in 5 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A512
    B5
    C8
    D6