Doubtnut Promotions Sticky

A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone will complete the remaining work in: /
A किसी निश्चित कार्य को 30 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 20% अधिक कार्य कुशल है | उन सभी ने एक साथ तीन दिनों तक कार्य किया | शेष कार्य पूरा करने में B को अकेले कितने दिन लगेंगे ?

A

15 days

B

12 days

C

20 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the work done by A, B, and C

1. Efficiency of A: A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)

2. Efficiency of B: B is 25% more efficient than A. Therefore, B's work rate is:
Work rate of B=Work rate of A×1.25=130×1.25=1.2530=5120=124 (work per day)

3. Efficiency of C: C is 20% more efficient than B. Therefore, C's work rate is:
Work rate of C=Work rate of B×1.20=124×1.20=1.2024=6120=120 (work per day)

Step 2: Calculate the combined work rate of A, B, and C

4. Combined work rate:
Combined work rate=Work rate of A+Work rate of B+Work rate of C
=130+124+120

To add these fractions, we need a common denominator. The least common multiple (LCM) of 30, 24, and 20 is 120.

Converting each fraction:
130=4120,124=5120,120=6120

Adding them together:
Combined work rate=4120+5120+6120=15120=18 (work per day)

Step 3: Calculate the work done in 3 days

5. Work done in 3 days:
Work done in 3 days=3×Combined work rate=3×18=38

Step 4: Calculate the remaining work

6. Remaining work:
Total work=1(since we consider the whole work as 1 unit)
Remaining work=138=58

Step 5: Calculate the time taken by B to complete the remaining work

7. Time taken by B to complete the remaining work:
Time=Remaining workWork rate of B=58124=58×24=1208=15 days

Final Answer:
B alone will complete the remaining work in 15 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be completed by B alone, in:
    A किसी निश्चित कार्य को 40 दिनों में पूरा कर सकता है | B, A की तुलना में 25% अधिक कार्य कुशल है तथा C, B की तुलना में 22% अधिक कार्य कुशल है | वे 5 दिनों तक एक साथ कार्य करते हैं | शेष कार्य अकेले पूरा करने में B को कितने दिन लगेंगे ?

    A20(12) days
    B16(15) days
    C20(34) days
    D16(35) days
  • Question 2 - Select One

    A can do a picec of work in 10 days and B is 25% more
    efficient than A. In what time will the work be finished if A
    and B work together ?

    A449 days
    B557 days
    C5 days
    D623 days
  • Question 3 - Select One

    A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?

    A214
    B257
    C245
    D203