Doubtnut Promotions Sticky

A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

A

1212 days

B

1523 days

C

10 days

D

845 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Determine the work done by A, B, and C in one day
- A can complete the task in 24 days, so A's work per day = 124 of the work.
- B can complete the task in 20 days, so B's work per day = 120 of the work.
- C can complete the task in 18 days, so C's work per day = 118 of the work.

Step 2: Calculate the total work
- To find a common measure of work, we can use the LCM of 24, 20, and 18.
- The LCM of 24, 20, and 18 is 360.
- Therefore, we can assume the total work = 360 units.

Step 3: Calculate the efficiency of A, B, and C
- A's efficiency = 36024=15 units/day.
- B's efficiency = 36020=18 units/day.
- C's efficiency = 36018=20 units/day.

Step 4: Calculate the combined work done by B and C in 6 days
- Combined efficiency of B and C = 18 + 20 = 38 units/day.
- Work done by B and C in 6 days = 38×6=228 units.

Step 5: Calculate the remaining work
- Remaining work = Total work - Work done by B and C
- Remaining work = 360228=132 units.

Step 6: Calculate the number of days A needs to finish the remaining work
- A's efficiency = 15 units/day.
- Days required by A to complete the remaining work = 13215.
- This simplifies to 845 days.

Final Answer
A will take 845 days to finish the remaining task.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
    A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?

    A9
    B17(12)
    C12(12)
    D7(12)
  • Question 2 - Select One

    A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining tasks is:
    A, B तथा C अकेले कार्य करते हुए किसी कार्य को क्रमशः 20, 16 तथा 30 दिनों में पूरा कर सकते हैं | यदि Aऔर B ने यह कार्य शुरू किया तथा उन्होंने 4 दिन कार्य करके छोड़ दिया , तो शेष कार्य पूरा करने में C को कितने दिन लगेंगे ?

    A13 days
    B1612 days
    C10 days
    D1212 days
  • Question 3 - Select One

    A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

    A9
    B712
    C1712
    D1212