Doubtnut Promotions Sticky

A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?

A

1712

B

712

C

1212

D

9

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the total work in units
A can complete the task in 24 days, B in 16 days, and C in 32 days. To find the total work, we can take the least common multiple (LCM) of these days.

- LCM of 24, 16, and 32 is 96 units.

Step 2: Calculate the work efficiency of A, B, and C
Now, we can calculate the work done by each person per day:

- A's efficiency = Total work / Days taken by A = 96 / 24 = 4 units/day
- B's efficiency = Total work / Days taken by B = 96 / 16 = 6 units/day
- C's efficiency = Total work / Days taken by C = 96 / 32 = 3 units/day

Step 3: Calculate the work done by A and C in 6 days
A and C work together for 6 days. Their combined efficiency is:

- Combined efficiency of A and C = A's efficiency + C's efficiency = 4 + 3 = 7 units/day

Now, we calculate the total work done by A and C in 6 days:

- Work done by A and C in 6 days = Combined efficiency × Number of days = 7 × 6 = 42 units

Step 4: Calculate the remaining work
The total work is 96 units, and A and C have completed 42 units. Therefore, the remaining work is:

- Remaining work = Total work - Work done by A and C = 96 - 42 = 54 units

Step 5: Calculate the time required by B to complete the remaining work
B's efficiency is 6 units/day. To find out how many days B will take to complete the remaining 54 units, we use the formula:

- Days required by B = Remaining work / B's efficiency = 54 / 6 = 9 days

Final Answer
B will take 9 days to complete the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

    A9
    B712
    C1712
    D1212
  • Question 2 - Select One

    A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
    A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

    A15(12)
    B11
    C13(15)
    D18
  • Question 3 - Select One

    A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
    A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

    A1212days
    B1523days
    C10days
    D845days