Ram and Shyam can complete a task in 623 days and 15 days respectively. They work together for 4 days and then Ram leaves. In how many days after Ram leaves, will Shyam complete the remaining task alone? /
राम तथा श्याम किसी कार्य को क्रमशः 623 दिनों में तथा 15 दिनों में पूरा कर सकते हैं | उन्होंने 4 दिनों तक साथ कार्य किया तथा फिर राम चला गया | राम के जाने के कितने दिनों बाद श्याम अकेला इस कार्य को पूरा कर पायेगा ?
2 days
3 days
4 days
112 days
To solve the problem step by step, we will follow these calculations:
Step 1: Convert the days into a fraction
Ram can complete the task in 623 days, which can be converted into an improper fraction:
623=203 days
Shyam can complete the task in 15 days.
Step 2: Determine the total work
Assuming the total work is represented as 60 units (a common multiple of the denominators), we can find the work done per day by each worker.
Step 3: Calculate Ram's work rate
Ram's work rate can be calculated as:
Ram's work rate=60 units203 days=60×320=9 units/day
Step 4: Calculate Shyam's work rate
Shyam's work rate can be calculated as:
Shyam's work rate=60 units15 days=4 units/day
Step 5: Calculate combined work rate
When Ram and Shyam work together, their combined work rate is:
Combined work rate=9+4=13 units/day
Step 6: Calculate work done in 4 days
In 4 days, the total work done by both of them is:
Work done in 4 days=13 units/day×4 days=52 units
Step 7: Calculate remaining work
The remaining work after 4 days is:
Remaining work=60 units−52 units=8 units
Step 8: Calculate time taken by Shyam to complete remaining work
Shyam will complete the remaining work alone. Since Shyam's work rate is 4 units/day, the time taken by Shyam to complete the remaining work is:
Time taken=8 units4 units/day=2 days
Final Answer
Thus, after Ram leaves, Shyam will take 2 days to complete the remaining task alone.
---
Ram can complete the task in 623 days, which can be converted into an improper fraction:
623=203 days
Shyam can complete the task in 15 days.
Assuming the total work is represented as 60 units (a common multiple of the denominators), we can find the work done per day by each worker.
Ram's work rate can be calculated as:
Ram's work rate=60 units203 days=60×320=9 units/day
Shyam's work rate can be calculated as:
Shyam's work rate=60 units15 days=4 units/day
When Ram and Shyam work together, their combined work rate is:
Combined work rate=9+4=13 units/day
In 4 days, the total work done by both of them is:
Work done in 4 days=13 units/day×4 days=52 units
The remaining work after 4 days is:
Remaining work=60 units−52 units=8 units
Shyam will complete the remaining work alone. Since Shyam's work rate is 4 units/day, the time taken by Shyam to complete the remaining work is:
Time taken=8 units4 units/day=2 days
Thus, after Ram leaves, Shyam will take 2 days to complete the remaining task alone.
Topper's Solved these Questions
Similar Questions
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View Solution
Knowledge Check
A and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?
A2 daysB3 daysC4 daysD112 daysRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
A5 daysB6 daysC10 daysD1012
A can complete a task in 18 days while B can complete the same task in 12 days. If both work together for 6 days, and then A leaves. In how many days will B complete the task?
A किसी कार्य को 18 दिनों में पूरा कर सकता है जबकि B उसी कार्य को 12 दिनों में पूरा कर सकता है। यदि दोनों 6 दिनों के लिए एक साथ कार्य करते हैं, और फिर A कार्य छोड़ देता है, तो B कार्य को कितने दिनों में पूरा करेगा?
View SolutionA and B can complete a piece of work in 20 days and 30 days respectively. A works full time while B works half of the time. In how many days the entire work will be completed?
A तथा B किसी कार्य को क्रमशः 20 दिनों तथा 30 दिनों में पूरा कर सकते हैं | A पूरे समय कार्य करता है जबकि B आधे समय कार्य करता है | पूरा कार्य कितने दिनों में समाप्त हो जाएगा?
View SolutionAmir and Akbar can finish a task in 30 days and 15 days, respectively. Akbar worked on the task for 8 days and left the job. In how many days can Amir alone finish the remaining work?
आमिर और अकबर क्रमशः 30 दिनों और 15 दिनों में एक कार्य पूरा कर सकते हैं। अकबर ने 8 दिनों तक कार्य किया और नौकरी छोड़ दी। शेष कार्य को आमिर अकेले कितने दिनों में पूरा कर सकता है?
View SolutionA, B and C can complete a piece of work in 36 days, 54 days and 108 days respectively. They started working together, but 9 days after the start of work, A quit working and B also stopped working 3 days before the work was completed. How many days did C work?
A, B और C, एक कार्य को क्रमशः 36 दिनों, 54 दिनों और 108 दिनों में पूरा कर सकते हैं | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन कार्य शुरू होने के 9 दिनों के बाद A ने कार्य करना छोड़ दिया और कार्य पूरा होने के 3 दिन पहले B ने भी कार्य करना छोड़ दिया | C ने कितने दिन कार्य किया?
View SolutionA, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionA, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?
View Solution