Doubtnut Promotions Sticky

Ram and Shyam can complete a task in 623 days and 15 days respectively. They work together for 4 days and then Ram leaves. In how many days after Ram leaves, will Shyam complete the remaining task alone? /
राम तथा श्याम किसी कार्य को क्रमशः 623 दिनों में तथा 15 दिनों में पूरा कर सकते हैं | उन्होंने 4 दिनों तक साथ कार्य किया तथा फिर राम चला गया | राम के जाने के कितने दिनों बाद श्याम अकेला इस कार्य को पूरा कर पायेगा ?

A

2 days

B

3 days

C

4 days

D

112 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Convert the days into a fraction
Ram can complete the task in 623 days, which can be converted into an improper fraction:
623=203 days
Shyam can complete the task in 15 days.

Step 2: Determine the total work
Assuming the total work is represented as 60 units (a common multiple of the denominators), we can find the work done per day by each worker.

Step 3: Calculate Ram's work rate
Ram's work rate can be calculated as:
Ram's work rate=60 units203 days=60×320=9 units/day

Step 4: Calculate Shyam's work rate
Shyam's work rate can be calculated as:
Shyam's work rate=60 units15 days=4 units/day

Step 5: Calculate combined work rate
When Ram and Shyam work together, their combined work rate is:
Combined work rate=9+4=13 units/day

Step 6: Calculate work done in 4 days
In 4 days, the total work done by both of them is:
Work done in 4 days=13 units/day×4 days=52 units

Step 7: Calculate remaining work
The remaining work after 4 days is:
Remaining work=60 units52 units=8 units

Step 8: Calculate time taken by Shyam to complete remaining work
Shyam will complete the remaining work alone. Since Shyam's work rate is 4 units/day, the time taken by Shyam to complete the remaining work is:
Time taken=8 units4 units/day=2 days

Final Answer
Thus, after Ram leaves, Shyam will take 2 days to complete the remaining task alone.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?

    A2 days
    B3 days
    C4 days
    D112 days
  • Question 2 - Select One

    Ram and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:

    A5 days
    B6 days
    C10 days
    D1012