A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

A

8

B

21

C

16

D

11

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we follow these calculations:

Step 1: Determine the work done by A and B in one day.
- A can finish the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can finish the work in 25 days, so B's work rate is:
Work rate of B=125 (work per day)

Step 2: Calculate the combined work done by A and B in one day.
- The combined work rate of A and B is:
Combined work rate=120+125
- To add these fractions, we need a common denominator. The LCM of 20 and 25 is 100.
120=5100,125=4100
- Therefore,
Combined work rate=5100+4100=9100

Step 3: Calculate the work done by A and B together in 5 days.
- In 5 days, the total work done by A and B is:
Work done in 5 days=5×9100=45100=920

Step 4: Calculate the remaining work.
- The total work is considered as 1 (or 100%).
- The remaining work after 5 days is:
Remaining work=1920=2020920=1120

Step 5: Calculate how many days A will take to finish the remaining work.
- A's work rate is 120 work per day. To find out how many days A needs to finish 1120 of the work, we set up the equation:
Days required by A=Remaining workWork rate of A=1120120=11 days

Final Answer:
A will take 11 more days to finish the remaining work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A512
    B5
    C8
    D6