A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य
करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन
लगेंगे ?
8
21
16
11
To solve the problem step by step, we follow these calculations:
Step 1: Determine the work done by A and B in one day.
- A can finish the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can finish the work in 25 days, so B's work rate is:
Work rate of B=125 (work per day)
Step 2: Calculate the combined work done by A and B in one day.
- The combined work rate of A and B is:
Combined work rate=120+125
- To add these fractions, we need a common denominator. The LCM of 20 and 25 is 100.
120=5100,125=4100
- Therefore,
Combined work rate=5100+4100=9100
Step 3: Calculate the work done by A and B together in 5 days.
- In 5 days, the total work done by A and B is:
Work done in 5 days=5×9100=45100=920
Step 4: Calculate the remaining work.
- The total work is considered as 1 (or 100%).
- The remaining work after 5 days is:
Remaining work=1−920=2020−920=1120
Step 5: Calculate how many days A will take to finish the remaining work.
- A's work rate is 120 work per day. To find out how many days A needs to finish 1120 of the work, we set up the equation:
Days required by A=Remaining workWork rate of A=1120120=11 days
Final Answer:
A will take 11 more days to finish the remaining work.
---
- A can finish the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can finish the work in 25 days, so B's work rate is:
Work rate of B=125 (work per day)
- The combined work rate of A and B is:
Combined work rate=120+125
- To add these fractions, we need a common denominator. The LCM of 20 and 25 is 100.
120=5100,125=4100
- Therefore,
Combined work rate=5100+4100=9100
- In 5 days, the total work done by A and B is:
Work done in 5 days=5×9100=45100=920
- The total work is considered as 1 (or 100%).
- The remaining work after 5 days is:
Remaining work=1−920=2020−920=1120
- A's work rate is 120 work per day. To find out how many days A needs to finish 1120 of the work, we set up the equation:
Days required by A=Remaining workWork rate of A=1120120=11 days
A will take 11 more days to finish the remaining work.
Topper's Solved these Questions
Similar Questions
A can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View SolutionA can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 7 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?
View Solution
Knowledge Check
A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?A16B8C21D11A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A512B5C8D6
A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?
View SolutionA man finish a piece of work in 15 days. A woman can complete the same work in 10 days. Both work together for 5 days, then the man leaves. How many days will be taken by the woman to finish the remaining work?
एक आदमी किसी कार्य 15 दिनों में पूरा करता है। एक महिला इसी कार्य को 10 दिनों में पूरा कर सकती है। दोनों 5 दिन तक साथ काम करते हैं, फिर आदमी इस कार्य को छोड़ देता है। शेष कार्य को पूरा करने में महिला को कितने दिन लगेंगे?
View SolutionA and B , working together, can complete a work in 16 days, C and A together can complete it in 32 days and C and B together can complete it in 24 days. They worked together for 12 days. In how many days will C can complete the remaining work ? /
A और B एक साथ कार्य करते हुए किसी कार्य को 16 दिनों में कर सकते हैं, C और A इस कार्य को 32 दिनों में कर सकते हैं और C और A इस कार्य को 32 दिनों में कर सकते हैं | उन्होंने 12 दिनों तक साथ कार्य किया | शेष कार्य समाप्त करने में C को कितने दिन लगेंगे ?
View Solution25 persons can complete a work in 60 days. They started the work. 10 people left the work after x days. If the whole work was completed in 80 days, then what is the value of x ?
25 व्यक्ति किसी कार्य को 60 दिनों में पूरा कर सकते हैं | उन्होंने कार्य शुरू किया | x दिनों के बाद 10 लोगों ने कार्य छोड़ दिया | यदि पूरा कार्य 80 दिनों में पूरा हुआ, तो x का मान ज्ञात करें |
View SolutionA can do a work in 30 days, B can do the same work in 48 days. After working alone for 20 days A left and B started working, how long will B take to complete the work?
A किसी कार्य को 30 दिनों में कर सकता है,B इसी कार्य को 48 दिनों में कर सकता है | 20 दिन तक अकेले कार्य करने के बाद A ने छोड़ दिया तथा B ने कार्य करना शुरू कर दिया |B को इस कार्य को पूरा करने में कितना समय लगेगा ?
View SolutionA can do a work in 12 days and B can do the same work in 16 days. If they work on it together for 4 days, then the fraction of the work that is left is:
A एक कार्य को 12 दिनों में कर सकता है और B उसी कार्य को 16 दिनों में कर सकता है। यदि वे 4 दिनों के लिए इस पर एक साथ कार्य करते हैं, फिर जो कार्य बचा है उसका अंश है:
View Solution