3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C starts work together, A and B left the work 2 days before the comple tion of the work, then the whole work will be finished in how many days?
3715
5715
5
7
The correct Answer is:B
To solve the problem, we need to determine how many days it takes for A, B, and C to complete the work together, given that A and B leave 2 days before the work is finished.
1. Determine the Work Rates of A, B, and C:
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
2. Calculate the Combined Work Rate of A, B, and C:
Combined Rate=110+112+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60.
- Convert each rate:
- 110=660
- 112=560
- 115=460
- Now, add them:
Combined Rate=6+5+460=1560=14
This means A, B, and C together can complete 14 of the work in one day.
3. Let the Total Work be 1 Unit:
- If the total work is 1 unit, then the time taken to complete the work by A, B, and C together is:
Time=1 unit14 unit/day=4 days
4. Determine the Work Done Before A and B Leave:
- A and B leave 2 days before the work is completed. Therefore, they work together for x−2 days, where x is the total number of days to complete the work.
- In the first x−2 days, A, B, and C work together:
Work done in (x−2) days=(x−2)×14
5. Calculate the Remaining Work Done by C:
- In the last 2 days, only C works:
Work done by C in 2 days=2×115=215
6. Set Up the Equation for Total Work:
- The total work done is equal to 1 unit:
(x−2)×14+215=1
7. Solve for x:
- Multiply the entire equation by 60 (the common denominator) to eliminate fractions:
15(x−2)+8=60
15x−30+8=60
15x−22=60
15x=82
x=8215=5715
Final Answer:
The whole work will be finished in 5715 days.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
Combined Rate=110+112+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60.
- Convert each rate:
- 110=660
- 112=560
- 115=460
- Now, add them:
Combined Rate=6+5+460=1560=14
This means A, B, and C together can complete 14 of the work in one day.
- If the total work is 1 unit, then the time taken to complete the work by A, B, and C together is:
Time=1 unit14 unit/day=4 days
- A and B leave 2 days before the work is completed. Therefore, they work together for x−2 days, where x is the total number of days to complete the work.
- In the first x−2 days, A, B, and C work together:
Work done in (x−2) days=(x−2)×14
- In the last 2 days, only C works:
Work done by C in 2 days=2×115=215
- The total work done is equal to 1 unit:
(x−2)×14+215=1
- Multiply the entire equation by 60 (the common denominator) to eliminate fractions:
15(x−2)+8=60
15x−30+8=60
15x−22=60
15x=82
x=8215=5715
The whole work will be finished in 5715 days.
Topper's Solved these Questions
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View Solution
Knowledge Check
3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?
A589B289C6D5A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
A12 daysB8 daysC9 daysD1012 days3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B and C start working together. After 2 days A left the work and after next 2 days C also left. Then find in how many days the whole work will be completed ?
A6B625C7D425
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution