3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C starts work together, A and B left the work 2 days before the comple tion of the work, then the whole work will be finished in how many days?

A

3715

B

5715

C

5

D

7

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days it takes for A, B, and C to complete the work together, given that A and B leave 2 days before the work is finished.

1. Determine the Work Rates of A, B, and C:
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.

2. Calculate the Combined Work Rate of A, B, and C:
Combined Rate=110+112+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60.
- Convert each rate:
- 110=660
- 112=560
- 115=460
- Now, add them:
Combined Rate=6+5+460=1560=14
This means A, B, and C together can complete 14 of the work in one day.

3. Let the Total Work be 1 Unit:
- If the total work is 1 unit, then the time taken to complete the work by A, B, and C together is:
Time=1 unit14 unit/day=4 days

4. Determine the Work Done Before A and B Leave:
- A and B leave 2 days before the work is completed. Therefore, they work together for x2 days, where x is the total number of days to complete the work.
- In the first x2 days, A, B, and C work together:
Work done in (x2) days=(x2)×14

5. Calculate the Remaining Work Done by C:
- In the last 2 days, only C works:
Work done by C in 2 days=2×115=215

6. Set Up the Equation for Total Work:
- The total work done is equal to 1 unit:
(x2)×14+215=1

7. Solve for x:
- Multiply the entire equation by 60 (the common denominator) to eliminate fractions:
15(x2)+8=60
15x30+8=60
15x22=60
15x=82
x=8215=5715

Final Answer:
The whole work will be finished in 5715 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?

    A589
    B289
    C6
    D5
  • A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days
  • 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B and C start working together. After 2 days A left the work and after next 2 days C also left. Then find in how many days the whole work will be completed ?

    A6
    B625
    C7
    D425