A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
20
30
18
24
The correct Answer is:A
To solve the problem step by step, we'll first determine the work done by A, B, and C, and then calculate how long A and B will take to finish the remaining work after C quits.
Step 1: Determine the work rates of A, B, and C.
- A can complete the job in 50 days, so A's work rate is:
Work rate of A=150 of the job per day
- B can complete the job in 75 days, so B's work rate is:
Work rate of B=175 of the job per day
- C can complete the job in 20 days, so C's work rate is:
Work rate of C=120 of the job per day
Step 2: Calculate the combined work rate of A, B, and C.
To find the combined work rate, we add their individual work rates:
Combined work rate=150+175+120
To add these fractions, we need a common denominator. The least common multiple (LCM) of 50, 75, and 20 is 300. Now we convert each fraction:
150=6300,175=4300,120=15300
Adding these together:
Combined work rate=6+4+15300=25300=112 of the job per day
Step 3: Calculate the total work done in 4 days.
Now, we calculate how much work A, B, and C can complete together in 4 days:
Work done in 4 days=4×112=412=13 of the job
Step 4: Determine the remaining work.
Since they completed 13 of the job, the remaining work is:
Remaining work=1−13=23 of the job
Step 5: Calculate the work rate of A and B together.
Next, we find the combined work rate of A and B:
Work rate of A and B=150+175
Using the same common denominator of 300:
150=6300,175=4300
Combined work rate of A and B=6+4300=10300=130 of the job per day
Step 6: Calculate the time taken by A and B to finish the remaining work.
To find the time T taken by A and B to complete the remaining 23 of the job:
T=Remaining workWork rate of A and B=23130=23×30=20 days
Final Answer:
A and B will take 20 days to finish the rest of the job.
- A can complete the job in 50 days, so A's work rate is:
Work rate of A=150 of the job per day
- B can complete the job in 75 days, so B's work rate is:
Work rate of B=175 of the job per day
Work rate of C=120 of the job per day
To find the combined work rate, we add their individual work rates:
Combined work rate=150+175+120
150=6300,175=4300,120=15300
Combined work rate=6+4+15300=25300=112 of the job per day
Now, we calculate how much work A, B, and C can complete together in 4 days:
Work done in 4 days=4×112=412=13 of the job
Since they completed 13 of the job, the remaining work is:
Remaining work=1−13=23 of the job
Next, we find the combined work rate of A and B:
Work rate of A and B=150+175
150=6300,175=4300
Combined work rate of A and B=6+4300=10300=130 of the job per day
To find the time T taken by A and B to complete the remaining 23 of the job:
T=Remaining workWork rate of A and B=23130=23×30=20 days
A and B will take 20 days to finish the rest of the job.
Topper's Solved these Questions
Similar Questions
A,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View SolutionA, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
View Solution
Knowledge Check
- Question 1 - Select One
If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
A9B6C3D4 - Question 2 - Select One
A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
A9B6C12D10 - Question 3 - Select One
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
A18 daysB24 daysC30 daysD36 days
A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
View SolutionA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
View Solution