Doubtnut Promotions Sticky

A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

A

20

B

30

C

18

D

24

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we'll first determine the work done by A, B, and C, and then calculate how long A and B will take to finish the remaining work after C quits.

Step 1: Determine the work rates of A, B, and C.
- A can complete the job in 50 days, so A's work rate is:
Work rate of A=150 of the job per day

- B can complete the job in 75 days, so B's work rate is:
Work rate of B=175 of the job per day

- C can complete the job in 20 days, so C's work rate is:
Work rate of C=120 of the job per day

Step 2: Calculate the combined work rate of A, B, and C.
To find the combined work rate, we add their individual work rates:
Combined work rate=150+175+120

To add these fractions, we need a common denominator. The least common multiple (LCM) of 50, 75, and 20 is 300. Now we convert each fraction:
150=6300,175=4300,120=15300

Adding these together:
Combined work rate=6+4+15300=25300=112 of the job per day

Step 3: Calculate the total work done in 4 days.
Now, we calculate how much work A, B, and C can complete together in 4 days:
Work done in 4 days=4×112=412=13 of the job

Step 4: Determine the remaining work.
Since they completed 13 of the job, the remaining work is:
Remaining work=113=23 of the job

Step 5: Calculate the work rate of A and B together.
Next, we find the combined work rate of A and B:
Work rate of A and B=150+175

Using the same common denominator of 300:
150=6300,175=4300
Combined work rate of A and B=6+4300=10300=130 of the job per day

Step 6: Calculate the time taken by A and B to finish the remaining work.
To find the time T taken by A and B to complete the remaining 23 of the job:
T=Remaining workWork rate of A and B=23130=23×30=20 days

Final Answer:
A and B will take 20 days to finish the rest of the job.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?

    A9
    B6
    C3
    D4
  • Question 2 - Select One

    A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?

    A9
    B6
    C12
    D10
  • Question 3 - Select One

    A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b.  24 days c. 30 days d. 36 days

    A18 days
    B24 days
    C30 days
    D36 days