Doubtnut Promotions Sticky

How many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?

A

20

B

21

C

45

D

63

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we will follow these steps:

Step 1: Determine the total work in terms of man-days.
Given that 15 men can complete 13 of the job in 7 days, we can calculate the total work in man-days.

Work done by 15 men in 7 days=15 men×7 days=105 man-days

Since this amount of work corresponds to 13 of the total job, we can find the total work (W) as follows:

W=105 man-days×3=315 man-days

Step 2: Calculate the number of men needed to complete the job in 5 days.
Now, we need to find out how many men (M) are required to complete the total work (315 man-days) in 5 days.

Using the formula for work:

Work=Number of Men×Days

We can rearrange this to find the number of men:

M=WD

Substituting the values we have:

M=315 man-days5 days=63 men

Final Answer:
Therefore, 63 men are needed to complete the job in 5 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    How many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?

    A20
    B21
    C45
    D63
  • Question 2 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • Question 3 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32