Doubtnut Promotions Sticky

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

A

4

B

5411

C

6411

D

4411

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to determine how many hours A and B need to work together each day to complete the work in 5 days.

Step 1: Calculate the total work done by A and B.

- A's Work Calculation:
A can complete the work in 6 days, working 8 hours a day.
Total work by A=6 days×8 hours/day=48 hours

- B's Work Calculation:
B can complete the work in 4 days, working 10 hours a day.
Total work by B=4 days×10 hours/day=40 hours

Step 2: Determine the total amount of work required.

The total work required to complete the task is the same as the work done by A or B, which is the maximum of the two:
Total Work=48 hours (A's work)

Step 3: Calculate the work done per hour by A and B.

- A's Work Rate:
Work rate of A=1 work48 hours=148 work/hour

- B's Work Rate:
Work rate of B=1 work40 hours=140 work/hour

Step 4: Combine their work rates.

To find the combined work rate of A and B:
Combined work rate=148+140

To add these fractions, we need a common denominator. The least common multiple of 48 and 40 is 240.

Converting the fractions:
148=5240,140=6240
So,
Combined work rate=5240+6240=11240 work/hour

Step 5: Calculate the total work needed in 5 days.

If they need to complete the work in 5 days, the total work done in 5 days at their combined work rate is:
Total work in 5 days=5 days×H hours/day×11240 work/hour
Setting this equal to 1 (the total work):
5H11240=1

Step 6: Solve for H.

Rearranging the equation:
H=2405×11=24055=4811

Step 7: Convert hours into a mixed number.

H=4411 hours

Final Answer:
A and B need to work together for approximately 4411 hours each day to complete the work in 5 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611

    A5511
    B5611
    C6511
    D6611
  • Question 2 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

    A5511
    B5611
    C6511
    D6611
  • Question 3 - Select One

    A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?

    A819
    B989
    C889
    D918