Doubtnut Promotions Sticky

x boys can do a piece of work in 24 days. In how much time (in days), 2x boys will do half of the work?

A

6

B

12

C

18

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the relationship between work, manpower, and time.

1. Understand the Work Done by x Boys:
- Given that x boys can complete a piece of work in 24 days, we can denote the total work as W.
- The work done by x boys in 24 days can be expressed as:
W=x×24

2. Determine the Work Done by 2x Boys:
- If 2x boys are working, they will have double the manpower compared to x boys.
- Therefore, the work done by 2x boys in one day is:
Work done in 1 day=2x

3. Calculate the Time Taken by 2x Boys to Complete the Full Work:
- The time taken (D) by 2x boys to complete the entire work W can be calculated using the formula:
W=Manpower×Days
- Rearranging gives:
D=WManpower=x×242x=242=12 days
- Thus, 2x boys can complete the entire work in 12 days.

4. Calculate the Time Taken to Complete Half of the Work:
- Since we need to find out how long it takes for 2x boys to complete half of the work, we take half of the total time:
Time for half of the work=122=6 days

Final Answer:
2x boys will take 6 days to complete half of the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the same piece of work?

    A16
    B15
    C17
    D18
  • Question 2 - Select One

    If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the. same piece of work?

    A16
    B15
    C17
    D18
  • Question 3 - Select One

    Some girls can do a piece of work in 18 days. In how much time (in days) two times the number of such girls will complete thrice of the work?

    A12
    B27
    C21
    D24