x boys can do a piece of work in 24 days. In how much time (in days), 2x boys will do half of the work?
6
12
18
8
The correct Answer is:A
To solve the problem step by step, we will use the relationship between work, manpower, and time.
1. Understand the Work Done by x Boys:
- Given that x boys can complete a piece of work in 24 days, we can denote the total work as W.
- The work done by x boys in 24 days can be expressed as:
W=x×24
2. Determine the Work Done by 2x Boys:
- If 2x boys are working, they will have double the manpower compared to x boys.
- Therefore, the work done by 2x boys in one day is:
Work done in 1 day=2x
3. Calculate the Time Taken by 2x Boys to Complete the Full Work:
- The time taken (D) by 2x boys to complete the entire work W can be calculated using the formula:
W=Manpower×Days
- Rearranging gives:
D=WManpower=x×242x=242=12 days
- Thus, 2x boys can complete the entire work in 12 days.
4. Calculate the Time Taken to Complete Half of the Work:
- Since we need to find out how long it takes for 2x boys to complete half of the work, we take half of the total time:
Time for half of the work=122=6 days
Final Answer:
2x boys will take 6 days to complete half of the work.
---
- Given that x boys can complete a piece of work in 24 days, we can denote the total work as W.
- The work done by x boys in 24 days can be expressed as:
W=x×24
- If 2x boys are working, they will have double the manpower compared to x boys.
- Therefore, the work done by 2x boys in one day is:
Work done in 1 day=2x
- The time taken (D) by 2x boys to complete the entire work W can be calculated using the formula:
W=Manpower×Days
- Rearranging gives:
D=WManpower=x×242x=242=12 days
- Thus, 2x boys can complete the entire work in 12 days.
- Since we need to find out how long it takes for 2x boys to complete half of the work, we take half of the total time:
Time for half of the work=122=6 days
2x boys will take 6 days to complete half of the work.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
Knowledge Check
- Question 1 - Select One
If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the same piece of work?
A16B15C17D18 - Question 2 - Select One
If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the. same piece of work?
A16B15C17D18 - Question 3 - Select One
Some girls can do a piece of work in 18 days. In how much time (in days) two times the number of such girls will complete thrice of the work?
A12B27C21D24
7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys can do 29/56 of the same work in 1 day, in how many days will 1 man do this work?
View Solution7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys can do 29/56 of the same work in 1 day, in how many days will 1 man do this work?
View SolutionA can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?
View SolutionA can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
View Solution35 boys can do a piece of work in 15 days. The work will completed in 25 days. How many boys did not turn up for the job?
View Solution