Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in
9 days
6 days
5 days
3 days
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Understand the given information
We know that a certain number of persons can complete a piece of work in 12 days. Let's denote the number of persons as P.
Step 2: Calculate the total work
The total work can be represented as:
Total Work=P×12 days
This means that P persons can complete P×12 units of work in 12 days.
Step 3: Determine the new number of persons
According to the problem, two times the number of persons will be working. Therefore, the new number of persons is:
2P
Step 4: Calculate the amount of work done by the new group
The new group of 2P persons will be doing work. Since they are twice as many, they will complete the same total work in less time.
Step 5: Calculate the time taken to complete half the work
We need to find out how long it will take for 2P persons to complete half of the total work. Half of the total work is:
Half Work=P×122=6P
Step 6: Calculate the time taken by 2P persons to complete half the work
The rate of work done by 2P persons is:
Work Rate=2P persons×Days
To find the time taken (let's denote it as T), we can set up the equation:
2P×T=6P
Step 7: Solve for T
Dividing both sides by 2P (assuming P≠0):
T=6P2P=3 days
Conclusion
Thus, two times the number of such persons will do half of the work in 3 days.
---
We know that a certain number of persons can complete a piece of work in 12 days. Let's denote the number of persons as P.
The total work can be represented as:
Total Work=P×12 days
This means that P persons can complete P×12 units of work in 12 days.
According to the problem, two times the number of persons will be working. Therefore, the new number of persons is:
2P
The new group of 2P persons will be doing work. Since they are twice as many, they will complete the same total work in less time.
We need to find out how long it will take for 2P persons to complete half of the total work. Half of the total work is:
Half Work=P×122=6P
The rate of work done by 2P persons is:
Work Rate=2P persons×Days
To find the time taken (let's denote it as T), we can set up the equation:
2P×T=6P
Dividing both sides by 2P (assuming P≠0):
T=6P2P=3 days
Thus, two times the number of such persons will do half of the work in 3 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
Some persons can do piece of work in 12 days. Two times the number of such persons will do half of the work in
(A) 9 days (B) 6 days (C) 5 days (D) 3 daysView SolutionSome persons can do a piece of work in 12 days. Two times the number of such persons will do half of that work in 6 days b. 4 days c. 3 days d. 12 days
View Solution
Knowledge Check
- Question 1 - Select One
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
A40B20C14D10 - Question 2 - Select One
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
A4B5C14D10 - Question 3 - Select One
x boys can do a piece of work in 24 days. In how much time (in days), 2x boys will do half of the work?
A6B12C18D8
If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days
View SolutionIf 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is
View Solutionx boys can do a piece of work in 24 days. In how much time (in days), 2x boys will do half of the work?
View SolutionIf 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
View SolutionSome girls can do a piece of work in 18 days. In how much time (in days) two times the number of such girls will complete thrice of the work?
View Solution