Doubtnut Promotions Sticky

Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in

A

9 days

B

6 days

C

5 days

D

3 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Understand the given information
We know that a certain number of persons can complete a piece of work in 12 days. Let's denote the number of persons as P.

Step 2: Calculate the total work
The total work can be represented as:
Total Work=P×12 days
This means that P persons can complete P×12 units of work in 12 days.

Step 3: Determine the new number of persons
According to the problem, two times the number of persons will be working. Therefore, the new number of persons is:
2P

Step 4: Calculate the amount of work done by the new group
The new group of 2P persons will be doing work. Since they are twice as many, they will complete the same total work in less time.

Step 5: Calculate the time taken to complete half the work
We need to find out how long it will take for 2P persons to complete half of the total work. Half of the total work is:
Half Work=P×122=6P

Step 6: Calculate the time taken by 2P persons to complete half the work
The rate of work done by 2P persons is:
Work Rate=2P persons×Days
To find the time taken (let's denote it as T), we can set up the equation:
2P×T=6P

Step 7: Solve for T
Dividing both sides by 2P (assuming P0):
T=6P2P=3 days

Conclusion
Thus, two times the number of such persons will do half of the work in 3 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10
  • Question 2 - Select One

    If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

    A4
    B5
    C14
    D10
  • Question 3 - Select One

    x boys can do a piece of work in 24 days. In how much time (in days), 2x boys will do half of the work?

    A6
    B12
    C18
    D8