P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?
P
Q
R
Both P and R
The correct Answer is:C
To determine who will complete the work first among P, Q, and R, we need to calculate the total time each person takes to complete the entire work based on the information given.
Step 1: Calculate the total time taken by P to complete the work.
- P can do 14 of the work in 10 days.
- Therefore, to complete the whole work, P will take:
Total time for P=10 days×4=40 days
Step 2: Calculate the total time taken by Q to complete the work.
- Q can do 40% of the work in 40 days, which is equivalent to 25 of the work.
- To find the total time for Q to complete the whole work, we can set up the equation:
Total time for Q=40 days×52=100 days
Step 3: Calculate the total time taken by R to complete the work.
- R can do 13 of the work in 13 days.
- Therefore, to complete the whole work, R will take:
Total time for R=13 days×3=39 days
Step 4: Compare the total times taken by P, Q, and R.
- Time taken by P = 40 days
- Time taken by Q = 100 days
- Time taken by R = 39 days
Step 5: Determine who completes the work first.
- Comparing the times, we see:
- P takes 40 days,
- Q takes 100 days,
- R takes 39 days.
Since 39 days (R) is less than both 40 days (P) and 100 days (Q), R will complete the work first.
Conclusion:
R will complete the work first in 39 days.
---
- P can do 14 of the work in 10 days.
- Therefore, to complete the whole work, P will take:
Total time for P=10 days×4=40 days
- Q can do 40% of the work in 40 days, which is equivalent to 25 of the work.
- To find the total time for Q to complete the whole work, we can set up the equation:
Total time for Q=40 days×52=100 days
- R can do 13 of the work in 13 days.
- Therefore, to complete the whole work, R will take:
Total time for R=13 days×3=39 days
- Time taken by P = 40 days
- Time taken by Q = 100 days
- Time taken by R = 39 days
- Comparing the times, we see:
- P takes 40 days,
- Q takes 100 days,
- R takes 39 days.
Since 39 days (R) is less than both 40 days (P) and 100 days (Q), R will complete the work first.
R will complete the work first in 39 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
X can do 14 of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first?
AXBYCZDboth X and Z - Question 2 - Select One
A can do 15 th part of the work in 12 days, B can do 60% of the work in 30 days and C can do 13 rd of the work in 15 days. Who will complete the work first?
AABBCCDA and B both - Question 3 - Select One
P can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?
APBQCRDS
Swaroop can do 1/3rd of a work in 12 days. He can do 3/4th of work in …………..days.
View SolutionA can do 14 part of a work in 21 days and B can do 14 part of a work in 7 days. In how many days will A and B complete the total work ?
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionIf P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?View SolutionP and Q can do a piece of work in 10 days, Q and R can do same work in 15 days, R and P can do the same work in 20 days. Then in how many days R will complete it alone.
View Solution