Doubtnut Promotions Sticky

If 9 men or 15 women can do a piece of work in 18 days working 9 hours a day. How many days will it take to complete a work twice as large with 6 men and 8 women working together 6 hours a day?

A

22 days

B

27.5 days

C

45 days

D

22.5 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by men and women, then calculate the total work required for the larger task, and finally find out how long it will take for 6 men and 8 women to complete that work.

Step 1: Determine the efficiency of men and women
Given:
- 9 men can complete the work in 18 days working 9 hours a day.
- 15 women can complete the same work in the same time.

Total work done by men:
Total Work=Number of Men×Days×Hours per Day×Efficiency of Men
Let the efficiency of men be m.
Total Work=9×18×9×m=1458m

Total work done by women:
Let the efficiency of women be w.
Total Work=15×18×9×w=2430w

Since both expressions represent the same total work:
1458m=2430w
Dividing both sides by 486 gives:
3m=5wmw=53

Step 2: Calculate total work for twice the amount
Since the work is now twice as large:
Total Work=2×1458m=2916m

Step 3: Calculate the combined efficiency of 6 men and 8 women
Using the ratio of efficiencies:
- Efficiency of 6 men: 6m
- Efficiency of 8 women: 8w

Now substituting w in terms of m:
w=3m58w=8×3m5=24m5

Combined efficiency of 6 men and 8 women:
Combined Efficiency=6m+24m5=30m+24m5=54m5

Step 4: Calculate the number of days required to complete the work
Let D be the number of days required to complete the work with 6 men and 8 women working 6 hours a day.
Total Work=Combined Efficiency×Days×Hours per Day
2916m=(54m5)×D×6

Now simplifying:
2916m=324mD5
Cancelling m from both sides (assuming m0):
2916=324D5
Multiplying both sides by 5:
14580=324D
Dividing both sides by 324:
D=14580324=45

Final Answer
The number of days required to complete the work is 45 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 4 men or 6 women can do a piece of work in 12 days workIng 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?

    A6 days
    B7 days
    C8 days
    D10 days
  • Question 2 - Select One

    If 3 men or 6 boy, can do a piece of work in 10 days, working 7 hours a day; how many days will it take to complete a piece of work twice as large with 6 men and 2 boy. 1% 'irking together for 8 hours a day? 6 b. 9 c. 812 d. 712

    A7 1/2 days
    B8 1/2 days
    C9 days
    D6 days
  • Question 3 - Select One

    9 women con complete a piece of work in 19 days. How
    many days will 18 women take to complete the same piece of
    work ?

    A12 days
    B6.5 days
    C9 days
    DNone of these