40 men and 20 women together can complete a work in 12 days and ratio of efficiency of a man to a woman is 2:3, find how many men are required to complete half of the work in 7 days?
A)70
B)35
C)30
D)60
The correct Answer is:D
To solve the problem step by step, we will follow these calculations:
Step 1: Calculate Total Work Done
We know that 40 men and 20 women can complete the work in 12 days.
- The efficiency of a man is given as 2 units.
- The efficiency of a woman is given as 3 units.
Total Efficiency Calculation:
- Efficiency of 40 men = 40 men × 2 units/man = 80 units
- Efficiency of 20 women = 20 women × 3 units/woman = 60 units
Total Efficiency of the group:
Total Efficiency=80+60=140 units/day
Total Work Calculation:
Total work can be calculated as:
Total Work=Total Efficiency×Time
Total Work=140 units/day×12 days=1680 units
Step 2: Calculate Half of the Total Work
Since we need to find how many men are required to complete half of the work:
Half of Total Work=16802=840 units
Step 3: Calculate the Required Efficiency to Complete Half Work in 7 Days
We need to find out how many men (let's denote this as m) are required to complete 840 units of work in 7 days.
Required Efficiency Calculation:
Required Efficiency=Half of Total WorkTime
Required Efficiency=840 units7 days=120 units/day
Step 4: Relate the Required Efficiency to the Number of Men
The efficiency of m men is:
Efficiency of m men=m×2 units/man
Setting this equal to the required efficiency:
m×2=120
Step 5: Solve for m
m=1202=60
Thus, the number of men required to complete half of the work in 7 days is 60.
Final Answer:
60 men are required.
---
We know that 40 men and 20 women can complete the work in 12 days.
- The efficiency of a woman is given as 3 units.
- Efficiency of 40 men = 40 men × 2 units/man = 80 units
- Efficiency of 20 women = 20 women × 3 units/woman = 60 units
Total Efficiency=80+60=140 units/day
Total work can be calculated as:
Total Work=Total Efficiency×Time
Total Work=140 units/day×12 days=1680 units
Since we need to find how many men are required to complete half of the work:
Half of Total Work=16802=840 units
We need to find out how many men (let's denote this as m) are required to complete 840 units of work in 7 days.
Required Efficiency=Half of Total WorkTime
Required Efficiency=840 units7 days=120 units/day
The efficiency of m men is:
Efficiency of m men=m×2 units/man
Setting this equal to the required efficiency:
m×2=120
m=1202=60
60 men are required.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 2 - Select One
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160 - Question 3 - Select One
3 men and 5 women together can complete a work in 6 days, whereas 4 men and 9 women together can doit in 4 days. How many women are required to do the same work in 7 days?
A15B12C14D10
Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 woment can complete the same piece of work ?
A. Ratio of efficiency of men to woment is 3:2.
B. 6 men & 6 women can complete the dame work in 4 days.View Solution12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
View Solution