A contractor employees 245 men who finish the 7/11th of total work in 54 days. Due to rain the work will stopped for 11days and 40% work also destroyed. After rain 41 people falls sick and were not able to do the work. In how many days the work will completed?
A
121
B
128
C
123
D
130
Text Solution
The correct Answer is:B
|
Updated on:21/07/2023
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-2)34videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
A2B3C4D5 - Question 2 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
A2B3C4D5 - Question 3 - Select One
A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?A10B12C9D15
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution