Doubtnut Promotions Sticky

Few men can do a piece of work in 8 day. Then start the work but every day 10 men left the work the work will be completed in 12 days. Find the number of men at the starting.

A

175

B

165

C

185

D

195

Text Solution
Verified by Experts

The correct Answer is:B

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    40 men can do a piece of work in 20 days. After how many days 8 men left the work that work should be done in 24 days?

    A8 days
    B12 days
    C6 days
    D4 days
  • Question 2 - Select One

    If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be

    A12 days
    B10 days
    C9 days
    D8 days
  • Question 3 - Select One

    60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

    A36
    B30
    C40
    D45