A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
514
532
528
495
The correct Answer is:C
Step by step video, text & image solution for A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-2)34videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View Solution
Knowledge Check
- Question 1 - Select One
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42 - Question 2 - Select One
A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
A162B234C262D81 - Question 3 - Select One
A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
A80B81C84D85
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
View Solution