Doubtnut Promotions Sticky

A contractor undertook to finish a road in 60 days and he employ 150 men. After 45 days he employed 130 more men, the work finished on time. Then find if more men were not employed then work will complete how much late?

A

13 days

B

10 days

C

15 days

D

23 days

Text Solution
Verified by Experts

The correct Answer is:A

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men
  • Question 2 - Select One

    A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :

    A45
    B40
    C35
    D30
  • Question 3 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A70
    B75
    C80
    D85