A contractor undertook to finish a road in 60 days and he employ 150 men. After 45 days he employed 130 more men, the work finished on time. Then find if more men were not employed then work will complete how much late?
13 days
10 days
15 days
23 days
The correct Answer is:A
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-2)34videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
A contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he emp,oyed to complete the work in time ?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men - Question 2 - Select One
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
A45B40C35D30 - Question 3 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A70B75C80D85
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?View Solution