A contractor undertakes to make a road in 180 days of 32.8 km long and employes 210 men. After 90 days he finds that only 12.3 km long road is made. How many extra men should he employee so that he is able to complete the work 6 days earlier (it is given that each new man is 50% more efficient than contractor had already hired).
108
110
112
115
The correct Answer is:B
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-2)34videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
A contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he emp,oyed to complete the work in time ?
View SolutionA contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time ?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A70B75C80D85 - Question 2 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A100B60C75DNone of these - Question 3 - Select One
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 men
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertook to dig a canal,6 kilometre long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been dug. How many more men must he employ to finish the work in time ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View Solution