A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
45
40
35
30
The correct Answer is:D
Step by step video, text & image solution for A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done (3)/(5) part of the work, the number of men he can withdraw so that the work may still be finished in time is : by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-2)34videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
A48B56C40D50 - Question 2 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
A40B50C48D56 - Question 3 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?A48B56C40D50
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View Solution