Doubtnut Promotions Sticky

A can do a task in 18 days. He works for 10 days and leaves. The remaining workin completed by B adn C. If they get Rs. 9000 for completing the work, then who receives more share in the earings?

A

C

B

A

C

B

D

Cannot say

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


A's 10 days work =1018=59
A completed more than half of the work.
Hence A gets more share.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • Question 2 - Select One

    A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • Question 3 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days