If 15 men 4 hours per day works for 14 days get Rs.35/- then how many men required if the work is 8 hours per day for 10 days they get 50/- ?
1 12
2 13
3 14
4 15
Answer : 4. "15" Explanation :Answer: D) 15 Explanation: We know M1×D1×H1W1
Related Solutions
Twelve (12) men work 8 hours per day and require 10 days to build a wall. If 8 men are available, how many hours per day must they work to finish the work in 8 days ?
View Solution24 men can do a work in 14 days by working 6 hours a day. If’ the work is to be completed in 8 days by working to *7 hours per day how many men are required?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View Solution24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per day can complete the same work?
View SolutionIf 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 4 men working 4 hours per day for 4 days complete 4.units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days ?
View SolutionTwelve (12) men work 8 hours a day and it takes them 10 days to build a wall. If 8 men are available, how many hours per day must be worked to complete the work in 8 days?
View Solution8 पुरुष प्रतिदिन 9 घंटे काम करते हुए एक काम 20 दिन में पूरा करते है। 7 पुरुष प्रतिदिन 10 घंटे काम करते हुए उसी काम को कितने दिन में पूरा करेंगे ?
View Solution8 पुरुष 9 घंटे प्रतिदिन काम करके एक काम को 20 दिनों में ख़त्म करते है , तो 7 पुरुष 10 घंटे प्रतिदिन काम करके कितने दिनों में काम ख़त्म करेंगे ?
View SolutionIf 10 men finish 10 unit work in 10 days at 10 hours per day, then how many units of work will 5 men complete in 5 days at 5 hours per day ?
View SolutionIf 10 men complete half work in 12 days when they work 8 hours per day, In how many days 18 men complete the full when they work 6 hours/day ?
View SolutionIf 30 men working 8 hours a day can complete a piece of work in 10 days, then how many hours per day must 40 men work so that they can complete it in 6 days?
View SolutionIf six men working 8 hours a day earn Rs. 840 per week then 9 men working 6 hours a day will earn per week-----
View Solution6 men can prepare 10 books in 8 days working 4 hours a day, then in how many days will 8 men working 2 hours a day prepare 15 books?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution12 men, working 8 hours a day, complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is_____
View Solution90 men can complete a work in 24 days working 8 hours a day. How many men are working 8 hours a day. How many men are required to complete the same work in 18 days working hours a day ?
View Solution