45 men working 9 hours per day dig 40 m deep. How many extra men should be put to dig to a depth of 56 m working 7 hours per day ?
1 36
2 61
3 48
4 54
Answer : 1. "36" Explanation :Answer: A) 36 Explanation: (45 x 9)/40 = (M x
Related Solutions
Eight men can dig a field 14 days,working 6 hours a day. In how many days can 7 men dig the same field, working 8 hours a day ?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View Solution24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per day can complete the same work?
View Solution8 पुरुष प्रतिदिन 9 घंटे काम करते हुए एक काम 20 दिन में पूरा करते है। 7 पुरुष प्रतिदिन 10 घंटे काम करते हुए उसी काम को कितने दिन में पूरा करेंगे ?
View Solution8 पुरुष 9 घंटे प्रतिदिन काम करके एक काम को 20 दिनों में ख़त्म करते है , तो 7 पुरुष 10 घंटे प्रतिदिन काम करके कितने दिनों में काम ख़त्म करेंगे ?
View Solution15 आदमी 20 मीटर लम्बी खाई को 8 घंटे / दिन का करके 18 दिन में खोदते है। 39 मीटर लम्बी खाई को 6 दिन में कितने आदमी खोद देगे यदि वे 9 घंटे/ दिन काम करें।
View Solution100 मजदूर 8 घण्टे प्रतिदिन काम करके 420 मी लम्बी. 8 मी चौड़ी, 3 मी गहरी खाई को 9 दिन में खोद लेते हैं, तो 490 मी लम्बी, 6 मी चौड़ी, 2 मी गहरी खाई को 7 घण्टे प्रतिदिन काम करके कितने मजदूर 6 दिनों में खोद लेंगे?
View SolutionIf 4 men working 4 hours per day for 4 days complete 4.units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days ?
View SolutionIf 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
View Solution24 men can do a work in 14 days by working 6 hours a day. If’ the work is to be completed in 8 days by working to *7 hours per day how many men are required?
View SolutionIf 30 men working 8 hours a day can complete a piece of work in 10 days, then how many hours per day must 40 men work so that they can complete it in 6 days?
View Solution27 men can dig a well in 20 days working 5 hours a day. They start digging it. After 4 days, 12 men leave. How hourse a day should the remaining men work to complete digging it by the scheduled date ?
View SolutionIf 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
View Solution110 मजदूर 8 घण्टे प्रतिदिन कार्य करके 880 मी लम्बी, 7 मी चौड़ी तथा 2 मी गहरी खाई को 8 दिन में खोद सकते हैं। 490 मी लम्बी, 8 मी चौड़ी, 3 मी गहरी खाई को 7 घण्टे प्रतिदिन कार्य करके 6 दिन में खोदने के लिए कितने मजदूर लगाने पड़ेंगे?
View SolutionTwelve (12) men work 8 hours per day and require 10 days to build a wall. If 8 men are available, how many hours per day must they work to finish the work in 8 days ?
View SolutionIf six men working 8 hours a day earn Rs. 840 per week then 9 men working 6 hours a day will earn per week-----
View Solutionयदि 50 आदमी 40 विवरों (holes) को 30 दिन में खोदते हैं तो 25 आदमी 20 विवरों को कितने दिनों में खोदेंगे?
View Solution4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?
View SolutionThirty men can dig a well in 10 days on working 8 hours a day. They started the work but after 2 days, 10 men left. How many hours a day should the remaining men work to complete it on time?
View SolutionIf 10 men finish 10 unit work in 10 days at 10 hours per day, then how many units of work will 5 men complete in 5 days at 5 hours per day ?
View Solution