A group of men can complete a job in K hours. After every 4 hours half the number of men working at that point of time leave the job. Continuing this way if the job is finished in 16 hours what is the
1 7 hrs
2 7.5 hrs
3 8 hrs
4 8.25 hrs
Answer : 2. "7.5 hrs" Explanation :Answer: B) 7.5 hrs Explanation: Let there
Related Solutions
2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?
View SolutionIf x can finish a job in 4 hours and y can finish the same job in 8 hours independently, then they together will finish the job in:
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionA person invests money in two different schemes for 5 years and 8 years at 12% and 10% simple interest, respectively. At the completion of each scheme he gets the same interest. The ratio of his investments is
View SolutionIf 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
View Solution15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days
View SolutionIf 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
View Solution33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?
View Solution33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View Solution16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
View SolutionSuresh can complete a job in 15 hours Ashutosh alone can complete the same job in 10 hours. Suresh works for 9 hours and then the remaining job is completed by Ashutosh. How many hours will it take Ashutosh to complete the remaining job alone?
View SolutionIf x people working together at the same rate can complete a job in h hours, what part of the same job can one person working alone complete in k hours?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionFifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?
View Solution18 men can complete two-third of a work in 24 hours. In how many hours will 16 men finish the remaining work?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solutionā¤¸āĨā¤āĨā¤¤ ā¤ā¤ ā¤ā¤žā¤Ž 8 ā¤ā¤ā¤āĨ ā¤ŽāĨā¤ ā¤¸ā¤Žā¤žā¤ĒāĨā¤¤ ā¤ā¤° ā¤¸ā¤ā¤¤ā¤ž ā¤šāĨāĨ¤ ā¤ā¤ ā¤ā¤ā¤āĨ ā¤ŽāĨā¤ ā¤¸āĨā¤āĨā¤¤ ā¤ā¤¸āĨ ā¤ā¤žā¤Ž ā¤ā¤ž ā¤ā¤ŋā¤¤ā¤¨ā¤ž ā¤šā¤ŋā¤¸āĨā¤¸ā¤ž ā¤ā¤° ā¤Ēā¤žā¤ā¤ā¤ž?
View SolutionāĻĒā§āĻ°āĻŋā§āĻž āĻ āĻĻā§āĻŦā§ āĻĒā§āĻ°āĻ¤ā§āĻ¯ā§āĻā§ āĻāĻ˛āĻžāĻĻāĻž āĻāĻžāĻŦā§ āĻāĻāĻāĻŋ āĻāĻžāĻ āĻ¯āĻĨāĻžāĻā§āĻ°āĻŽā§ 10 āĻāĻ¨ā§āĻāĻžā§ āĻ 12 āĻāĻ¨ā§āĻāĻžā§ āĻāĻ°āĻ¤ā§ āĻĒāĻžāĻ°ā§ | āĻ¤āĻžāĻ°āĻž āĻ¯āĻĻāĻŋ āĻāĻāĻ¸āĻā§āĻā§ āĻāĻ āĻāĻžāĻāĻāĻŋ āĻāĻ°ā§ āĻ¤āĻŦā§ āĻāĻ¤ āĻāĻ¨ā§āĻāĻžā§ āĻāĻžāĻāĻāĻŋ āĻļā§āĻˇ āĻāĻ°āĻŦā§ āĻšāĻŋāĻ¸āĻžāĻŦ āĻāĻ°ā§ |
View Solution