A B and C can complete a piece of work in 10 12 and 15 days respectively They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left.
1 4 days
2 5 days
3 7 days
4 8 days
Answer : 3. "7 days"
Related Solutions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? b. c. d.
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution3 men A, B, C can do a piece of work in 10, 12 and 15 days respectively. If A, B, C started working together, but after 2 days A left the work and after 2 days C also left the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 12, 15 and 18 days respectively. They started working together, but after 2 days A left the work and B left 3 days before the completion of that work. In how many days the whole work was completed?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View Solution3 men A, B and C can do a piece of work in 10, 12 and 15 days respectively. All three started working together but after 2 days A left the work and B left the work 1 day before the completion of the work. How long did it take to finish the whole work?
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionP, Q and R alone can complete a work in 12. 15 and 20 days respectively. In how many days will they together complete the same work?
View SolutionA, B और C किसी काम को क्रमश: 10 , 12 तथा 15 दिन में पूरा कर सकते है A ने काम पूरा होने से 5 दिन पहले काम छोड़ दिया और B ने A के काम छोड़ने के 2 दिन बाद काम छोड़ दिया । समस्त काम पूरा करने के लिए कितने दिनों की आवश्यकता होगी ?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.
b.
c.
d.
View Solution3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B and C start working together. After 2 days A left the work and after next 2 days C also left. Then find in how many days the whole work will be completed ?
View SolutionA, B and C can do a piece of work in 24, 30 and 40 days respectively. They started working together but C left the work 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View SolutionA, B and C take 36 days, 54 days and 72 days respectively to finish a piece of work. The three started working together. A left the work 8 days before the end of the work and B left 12 days before the completion of the work. For how many days did C work?
View Solution