40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day 5 men left the job. The work would have been completed in
1
2
3 52 days
4 50 days
Answer : 1. ""
Related Solutions
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
View Solution40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
View Solution60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View SolutionIf 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.
View SolutionIf 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.
View Solution40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in 40 लोग किसी काम को 40 दिनों में कर सकते हैं। उन्होंने एक साथ काम करना शुरू किया। लेकिन प्रत्येक 10 दिन के अंतराल पर 5 लोग काम छोड़ देते हैं, तो काम कितने दिनों में समाप्त होगा?
View Solution50 men can complete a work in 50 days. They started working together. But at the end of every 10th day 5 men come, then in how much time will the work be completed?
View Solutionयदि 40 पुरुष प्रतिदिन 12 घंटे कार्य करते हुए किसी कार्य को 8 दिनों में पूर्ण कर सकते हैं, तो कितने पुरुष प्रतिदिन 4 घंटे कार्य करते हुए - उसी कार्य को 16 दिनों में पूर्ण कर सकते हैं?
View SolutionIf 20 men can do a piece of work in 40 days, then when should 4 men leave the work so that the work is completed in 48 days?
View SolutionIf 30 men working 8 hours a day can complete a piece of work in 10 days, then how many hours per day must 40 men work so that they can complete it in 6 days?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution16 men can do a piecec of work in 10 days. How many men are needed to complete the work in 40 days?
View Solution12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View Solution5 men can do a piece of work in 4 days, the number of days in which 10 men can complete the work will be
View Solution48 आदमी किसी काम को 40 दिनों में पूरा कर सकते हैं। उसी को 60 आदमी कितने दिनों में पूरा कर सकेगा ?
View SolutionIf 24 men can complete a work in 40 days, then l/3rd of total men will complete the same work in:
View Solution5 men can do a piece of work in 10 days. How many men will be required to complete the work in 5 days?
View Solution12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start’ working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to Complete the remaining work, if it is to be completed in 3 days?
View Solution