A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?
1 7
2 8
3 9
4 10
Answer : 1. "7" Explanation :Answer: A) 7 Explanation: As the work is sameM
Related Solutions
A contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View Solution140 men were employed to finish a piece of work in 80 days. After 50 days 10 more men were employed. After how many days will the work be finished now?
View Solution8 men can finish a work in 40 days .If 2 more men would join them ,then how much days will required to finish the work ?
View Solution3 men can finish a work in 6 days After 2 days of starting their work, 3 more men came. the rest of the work will be finished
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution10 men can paint a wall in 8 days. If the painting work is to be finished in 4 days, how many more men will have to be employed?
View Solution60 men can finish a work in 50 days. If 20 men join the work every 10 days, then in how many days will the work be finished?
View SolutionSome men can finish a work in 80 days. If 10 more men were at work, the work would have been finished 20 days earlier. How many men were at work in the beginning?
View Solution120 men working 10 hours a day can finish a piece of work in 85 days. After 10 days all the men went on strike and the work was stopped for 25 days. In order to finish the work on time, additional men should be employed so that they can finish the work on time by working 8 hours a day?
View Solution2 पुरुष और 7 लड़के एक कार्य को 4 दिनों में समाप्त कर सकते हैं जबकि 4 पुरुष और 4 लड़के उसी कार्य को 3 दिनों में समाप्त कर सकते हैं। एक पुरुष या एक लड़का वह कार्य कितने दिन में समाप्त कर सकता है?
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 more men join the work.
View SolutionA certain number of men can do a work in 60 days. If there were 8 men less it could be finished in 10 days more. How many men are there?
View SolutionA certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View Solution15 men would finish a piece of work in 210 days. But at the end of every 10 days. 15 additional men are employed. In how many days will it be finished ?
View Solution10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View Solution9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be
View Solution