A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was doneso he put on 25 extra men. By how much time did he exce
1 2 days
2 3 days
3 4 days
4 5 days
Answer : 1. "2 days" Explanation :Answer: A) 2 days Explanation: work done=t
Related Solutions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only of the work How many extra days, than the scheduled time are required?
View SolutionA contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he emp,oyed to complete the work in time ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View SolutionA piece of work was to be completed in 40 days a number of men employed upon it did only half the work in 24 days, 16 more men were then set on, and the work was completed in the specified time, how many men were employed at first ?
View SolutionA contractor employs 36 men on a job and they do 1/2 of the work in 16 days. He employs 12 additional men to complete the remainder of the work. In how many days will the remaining work be finished?
View SolutionA contractor undertook to build a road in 120 days. He employed 100 men and after 45 days he found that only 1/4th part was made. How many more persons should he employ to complete the work on time?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that of the work was still to be done. How many more men were required to complete the work in stipulated time?
View SolutionA contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time ?
View SolutionA contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?View Solution