Doubtnut Promotions Sticky

A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

A

5

B

8

C

3

D

4

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work rates of A, B, and C, and then calculate how many days C requires to finish the remaining work after A and B have worked.

Step 1: Determine the work rates of A, B, and C

1. A and B together can complete the job in 8 days.
- Work done by A and B in one day = 1/8 of the job.

2. B and C together can complete the job in 12 days.
- Work done by B and C in one day = 1/12 of the job.

Step 2: Express the work rates

Let:
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c

From the above information:
- a+b=18 (1)
- b+c=112 (2)

Step 3: Find the individual work rates

We can express c in terms of b using equation (2):
- c=112b

Now substitute c into equation (1):
- a+b=18
- a+b+(112b)=18+112

Step 4: Find a common denominator and solve for a

The common denominator for 8 and 12 is 24:
- 324+224=524

So, we have:
- a+(112b)=524
- This simplifies to a+112b=524

Now, substituting b=18a:
- a+112(18a)=524

Step 5: Solve for a and b

After substituting and simplifying, we can find the values of a and b:
- a=124
- b=18124=112

Now substituting b back to find c:
- c=112b=112112=0

Step 6: Calculate work done by A and B in 4 days

- Work done by A and B in 4 days:
- Work done = 4×(a+b)=4×18=48=12

Step 7: Calculate work done by B in 2 more days

- Work done by B in 2 days:
- Work done = 2×b=2×112=212=16

Step 8: Total work done and remaining work

Total work done by A and B:
- Total work done = 12+16=36+16=46=23

Remaining work:
- Total work = 1 (whole job) - 23=13

Step 9: Calculate how many days C requires to finish the remaining work

Since C's work rate is c=112:
- Days required by C to complete 13 of the work:
- Work done by C in one day = 112
- Days required = Remaining work / C's work rate = 1/31/12=1/3×12/1=4 days.

Final Answer

C requires 4 days to complete the remaining work.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • Question 2 - Select One

    A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • Question 3 - Select One

    A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

    A12
    B16
    C20
    D24