A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?
5
8
3
4
The correct Answer is:D
Step by step video, text & image solution for A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Knowledge Check
- Question 1 - Select One
A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in
A12 daysB14 daysC16 daysD24 days - Question 1 - Select One
A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 days - Question 1 - Select One
A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
A12B16C20D24 - Question 1 - Select One
X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
A10 daysB12 daysC15 daysD18 days - Question 1 - Select One
A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
A60B30C45D40 - Question 1 - Select One
P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
A15B10C8D12 - Question 1 - Select One
P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
A12B10C15D8 - Question 1 - Select One
A and B finish a job in 12 days. While A,B and C can finish it in 8 days. C alone will finish the job in-
A14 daysB16 daysC10 daysD24 days
Similar Questions
(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is
View Solution