Doubtnut Promotions Sticky

A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

A

5

B

8

C

3

D

4

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • Question 1 - Select One

    A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days
  • Question 1 - Select One

    A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

    A12
    B16
    C20
    D24
  • Question 1 - Select One

    X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

    A10 days
    B12 days
    C15 days
    D18 days
  • Question 1 - Select One

    A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone

    A60
    B30
    C45
    D40
  • Question 1 - Select One

    P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.

    A15
    B10
    C8
    D12
  • Question 1 - Select One

    P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.

    A12
    B10
    C15
    D8
  • Question 1 - Select One

    A and B finish a job in 12 days. While A,B and C can finish it in 8 days. C alone will finish the job in-

    A14 days
    B16 days
    C10 days
    D24 days

Similar Questions