Doubtnut Promotions Sticky

A certain work is completed by A and B together in 10 days.
If A had worked at twice the speed and B had worked at half
his speed it would have taken them 8 days to finish the
work. Find the time in which B can alone finish the work.

A

20 days

B

24 days

C

30 days

D

32 days

Text Solution
Verified by Experts

The correct Answer is:(a)


Given, A certain work is completed by A and B together
in 10 days.
Let the number of days taken by A alone be 'a' and by
B alone be 'b'
In 1 day,
A completes 1/a part and B completes 1/b part.
1/a+1/b+1/10(1)
Now, if A had worked at twice the speed and B had
worked at half his speed it would have taken them
8 days to finish the work.
thus, 2/a+1/2b=1/8(2)
2×(1)(2)
2/b1/2b=1/51/8
3/2b=3/40
b=20 days

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B completed a work together in 8 days. Had A worked at twice the speed and B at one-third of his speed it would have taken them 6 days to complete the job. How much time would it take for B alone to do the work?

    A10
    B20
    C15
    D25
  • Question 2 - Select One

    A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?

    A50 days
    B60 days
    C48 days
    D54 days
  • Question 3 - Select One

    A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

    A18 days
    B21 days
    C24 days
    D27 days