8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed
7 days
6 days
5.25 days
3.7 days
The correct Answer is:(d)
To solve the problem step by step, let's break it down systematically.
Step 1: Determine the work done by men and women
Let the work done by one woman in one day be w. Therefore, the work done by one man in one day will be 2w (since a woman does half the work of a man).
Step 2: Calculate total work done by 8 men and 5 women in 7 days
The total work done by 8 men and 5 women in one day can be calculated as follows:
- Work done by 8 men in one day: 8×2w=16w
- Work done by 5 women in one day: 5×w=5w
Thus, the total work done in one day by 8 men and 5 women is:
16w+5w=21w
Since they complete the work in 7 days, the total work W can be calculated as:
W=(Work done in one day)×(Number of days)=21w×7=147w
Step 3: Calculate work done by 9 men and 3 women in 4 days
Now, 9 men and 3 women start working for 4 days. The work done in one day by 9 men and 3 women is:
- Work done by 9 men in one day: 9×2w=18w
- Work done by 3 women in one day: 3×w=3w
Thus, the total work done in one day by 9 men and 3 women is:
18w+3w=21w
The work done in 4 days is:
Work done in 4 days=21w×4=84w
Step 4: Calculate remaining work after 4 days
The remaining work after 4 days is:
Remaining work=Total work−Work done in 4 days=147w−84w=63w
Step 5: Calculate the new work team after changes
After 4 days, 4 men leave and 4 new women join. The new team consists of:
- Remaining men: 9−4=5
- Total women now: 3+4=7
The work done in one day by the new team is:
- Work done by 5 men in one day: 5×2w=10w
- Work done by 7 women in one day: 7×w=7w
Thus, the total work done in one day by the new team is:
10w+7w=17w
Step 6: Calculate the number of days to complete the remaining work
To find out how many more days are needed to complete the remaining work of 63w:
Days required=Remaining workWork done in one day=63w17w=6317≈3.71 days
Final Answer
Thus, the work will be completed in approximately 3.71 days.
---
Let the work done by one woman in one day be w. Therefore, the work done by one man in one day will be 2w (since a woman does half the work of a man).
The total work done by 8 men and 5 women in one day can be calculated as follows:
- Work done by 8 men in one day: 8×2w=16w
- Work done by 5 women in one day: 5×w=5w
16w+5w=21w
W=(Work done in one day)×(Number of days)=21w×7=147w
Now, 9 men and 3 women start working for 4 days. The work done in one day by 9 men and 3 women is:
- Work done by 9 men in one day: 9×2w=18w
- Work done by 3 women in one day: 3×w=3w
18w+3w=21w
Work done in 4 days=21w×4=84w
The remaining work after 4 days is:
Remaining work=Total work−Work done in 4 days=147w−84w=63w
After 4 days, 4 men leave and 4 new women join. The new team consists of:
- Remaining men: 9−4=5
- Total women now: 3+4=7
- Work done by 5 men in one day: 5×2w=10w
- Work done by 7 women in one day: 7×w=7w
10w+7w=17w
To find out how many more days are needed to complete the remaining work of 63w:
Days required=Remaining workWork done in one day=63w17w=6317≈3.71 days
Thus, the work will be completed in approximately 3.71 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
8 men and 4 women together can complete a piece of work in
6 days. The work done by a man in one day is diuble the
work done by a woman in one day. If 8 men and 4 women
started working and after 2 days 4 men left and 4 new women
joined, in how many more days will the work be complete?A5 daysB8 daysC6 daysD4 days8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
A5 daysB8 daysC6 daysD4 days8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 daysAQuantity I= Quantity II or No relationBQuantity I≥ Quantity IICQuantity I< Quantity IIDQuantity I le Quantity II
3 men or 4 women can do a piece of work in 43 days. In how many days 7 men & 5 women can do the same work ?
View Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution