Doubtnut Promotions Sticky

8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

A

7 days

B

6 days

C

5.25 days

D

3.7 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(d)


To solve the problem step by step, let's break it down systematically.

Step 1: Determine the work done by men and women
Let the work done by one woman in one day be w. Therefore, the work done by one man in one day will be 2w (since a woman does half the work of a man).

Step 2: Calculate total work done by 8 men and 5 women in 7 days
The total work done by 8 men and 5 women in one day can be calculated as follows:
- Work done by 8 men in one day: 8×2w=16w
- Work done by 5 women in one day: 5×w=5w

Thus, the total work done in one day by 8 men and 5 women is:
16w+5w=21w

Since they complete the work in 7 days, the total work W can be calculated as:
W=(Work done in one day)×(Number of days)=21w×7=147w

Step 3: Calculate work done by 9 men and 3 women in 4 days
Now, 9 men and 3 women start working for 4 days. The work done in one day by 9 men and 3 women is:
- Work done by 9 men in one day: 9×2w=18w
- Work done by 3 women in one day: 3×w=3w

Thus, the total work done in one day by 9 men and 3 women is:
18w+3w=21w

The work done in 4 days is:
Work done in 4 days=21w×4=84w

Step 4: Calculate remaining work after 4 days
The remaining work after 4 days is:
Remaining work=Total workWork done in 4 days=147w84w=63w

Step 5: Calculate the new work team after changes
After 4 days, 4 men leave and 4 new women join. The new team consists of:
- Remaining men: 94=5
- Total women now: 3+4=7

The work done in one day by the new team is:
- Work done by 5 men in one day: 5×2w=10w
- Work done by 7 women in one day: 7×w=7w

Thus, the total work done in one day by the new team is:
10w+7w=17w

Step 6: Calculate the number of days to complete the remaining work
To find out how many more days are needed to complete the remaining work of 63w:
Days required=Remaining workWork done in one day=63w17w=63173.71 days

Final Answer
Thus, the work will be completed in approximately 3.71 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    8 men and 4 women together can complete a piece of work in
    6 days. The work done by a man in one day is diuble the
    work done by a woman in one day. If 8 men and 4 women
    started working and after 2 days 4 men left and 4 new women
    joined, in how many more days will the work be complete?

    A5 days
    B8 days
    C6 days
    D4 days
  • Question 2 - Select One

    8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?

    A5 days
    B8 days
    C6 days
    D4 days
  • Question 3 - Select One

    8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
    Quantity I: more days required to complete the work
    II: 5 days

    AQuantity I= Quantity II or No relation
    BQuantity I Quantity II
    CQuantity I< Quantity II
    DQuantity I le Quantity II