Doubtnut Promotions Sticky

R is 1.5 times as efficient as that of P, and Q takes half time
as compared to that of R. If R and P takes 2 2/5 days to
complete half of the work then find the time taken by R and ltbegt Q together to complete the whole work?

A

213days

B

313days

C

113days

D

223days

Text Solution
Verified by Experts

The correct Answer is:(d)


Let the efficiency of R and P be 3x and 2x unit/ day resectively
Efficiency of Q = 6X units/ day
Total work=125×2×5x=24x units
Required time =24x9x=223 days

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.

    A9 days
    B12 days
    C18 days
    D24 days
  • Question 2 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 3 - Select One

    P, Q and R alone can complete a work in 12. 15 and 20 days respectively. In how many days will they together complete the same work?

    A4
    B5
    C6
    D3.5