X' can complete a work in 40 days while Y is 20% more effi-
cient then 'X' .'Y' worked for 8 days and lift, remaining work is
completed by 'Z' in 20 days. Find in how many days 'Z' can ltbegt complete the whole work alone?

A

27 days

B

21 days

C

18 days

D

26 days

Text Solution
Verified by Experts

The correct Answer is:(d)


Y Can complete work alone in
=40×56=33 days (approx)
Let Z alone can complete work in 't' days.
ATQ,
833+20t=1
20t=2533X=20×3325=26 days (approx)

Updated on:21/07/2023
Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

    A10 days
    B9 days
    C12 days
    D15 days