X' can complete a work in 40 days while Y is 20% more effi-
cient then 'X' .'Y' worked for 8 days and lift, remaining work is
completed by 'Z' in 20 days. Find in how many days 'Z' can ltbegt complete the whole work alone?
27 days
21 days
18 days
26 days
The correct Answer is:(d)
Y Can complete work alone in
=40×56=33 days (approx)
Let Z alone can complete work in 't' days.
ATQ,
833+20t=1
⇒20t=2533⇒X=20×3325=26 days (approx)
Topper's Solved these Questions
Similar Questions
Knowledge Check
A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 daysA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
A10 daysB9 daysC12 daysD15 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionIf C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
View SolutionIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View Solution