A alone can do a work in 20 days. The ratio of time taken by ltbegt A and B to do the same work is 4:3 Then, find in how many
days both will complete the work together ?
7.25 days
12 days
8 days
8.5 days
The correct Answer is:(d)
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A in one day.
A can complete the work in 20 days. Therefore, the amount of work done by A in one day is:
Work done by A in one day=120
Step 2: Find the time taken by B to complete the work.
The ratio of the time taken by A and B is given as 4:3. Let the time taken by A be 4x and the time taken by B be 3x. Since A takes 20 days to complete the work, we can set up the equation:
4x=20⟹x=5
Now, substituting x back to find the time taken by B:
Time taken by B=3x=3×5=15 days
Step 3: Determine the work done by B in one day.
Now, we can find the work done by B in one day:
Work done by B in one day=115
Step 4: Calculate the combined work done by A and B in one day.
To find the total work done by both A and B together in one day, we add their individual work rates:
Combined work done in one day=120+115
To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60. Thus, we convert the fractions:
120=360,115=460
Now, adding these:
Combined work done in one day=360+460=760
Step 5: Calculate the total time taken by A and B to complete the work together.
If A and B together can complete 760 of the work in one day, then the total time taken to complete 1 whole work is the reciprocal of this rate:
Total time taken=1760=607 days
Final Answer:
Thus, A and B together will complete the work in 607 days, which is approximately 8.57 days.
---
A can complete the work in 20 days. Therefore, the amount of work done by A in one day is:
The ratio of the time taken by A and B is given as 4:3. Let the time taken by A be 4x and the time taken by B be 3x. Since A takes 20 days to complete the work, we can set up the equation:
Now, we can find the work done by B in one day:
To find the total work done by both A and B together in one day, we add their individual work rates:
If A and B together can complete 760 of the work in one day, then the total time taken to complete 1 whole work is the reciprocal of this rate:
Thus, A and B together will complete the work in 607 days, which is approximately 8.57 days.
Topper's Solved these Questions
Similar Questions
A alone can do a work in 40 days. The ratio of time taken by A and B to do the same work is 5: 3. Then, find in how many days both will complete the work together?
View SolutionA can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View Solution
Knowledge Check
- Question 1 - Select One
P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
A48 daysB42 daysC45 daysD51 days - Question 2 - Select One
A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
A1. 15B2. 18C3. 20D4. 30 - Question 3 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA can do a certain work in 15 days, while working together, A and B can do the same work in 7.5 days. How many days will B alone take to do the same work ?
View SolutionA can do a certain work in 15 days, while working together, A and B can do the same work in 7.5 days. How many days will B alone take to do the same work?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution