Doubtnut Promotions Sticky

A alone can do a work in 20 days. The ratio of time taken by ltbegt A and B to do the same work is 4:3 Then, find in how many
days both will complete the work together ?

A

7.25 days

B

12 days

C

8 days

D

8.5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(d)


To solve the problem, we will follow these steps:

Step 1: Determine the work done by A in one day.
A can complete the work in 20 days. Therefore, the amount of work done by A in one day is:

Work done by A in one day=120

Step 2: Find the time taken by B to complete the work.
The ratio of the time taken by A and B is given as 4:3. Let the time taken by A be 4x and the time taken by B be 3x. Since A takes 20 days to complete the work, we can set up the equation:

4x=20x=5

Now, substituting x back to find the time taken by B:

Time taken by B=3x=3×5=15 days

Step 3: Determine the work done by B in one day.
Now, we can find the work done by B in one day:

Work done by B in one day=115

Step 4: Calculate the combined work done by A and B in one day.
To find the total work done by both A and B together in one day, we add their individual work rates:

Combined work done in one day=120+115

To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60. Thus, we convert the fractions:

120=360,115=460

Now, adding these:

Combined work done in one day=360+460=760

Step 5: Calculate the total time taken by A and B to complete the work together.
If A and B together can complete 760 of the work in one day, then the total time taken to complete 1 whole work is the reciprocal of this rate:

Total time taken=1760=607 days

Final Answer:
Thus, A and B together will complete the work in 607 days, which is approximately 8.57 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

    A48 days
    B42 days
    C45 days
    D51 days
  • Question 2 - Select One

    A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?

    A1. 15
    B2. 18
    C3. 20
    D4. 30
  • Question 3 - Select One

    Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42