Doubtnut Promotions Sticky

Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?

A

5 days

B

4 days

C

6 days

D

3 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(c)


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the efficiencies of Raja and Baja
- Raja can complete the work in 20 days, so his efficiency is:
Efficiency of Raja=120 work/day=3 units/day
- Baja can complete the work in 15 days, so his efficiency is:
Efficiency of Baja=115 work/day=4 units/day

Step 2: Calculate the total work
- The least common multiple (LCM) of 20 and 15 is 60, which we will take as the total work:
Total Work=60 units

Step 3: Calculate the work done by Raja in the last 6 days
- Raja finishes the remaining work in 6 days. The work done by Raja in these 6 days is:
Work done by Raja=Days×Efficiency=6×3=18 units

Step 4: Calculate the remaining work after Raja's contribution
- The remaining work after Raja's contribution is:
Remaining Work=Total WorkWork done by Raja=6018=42 units

Step 5: Calculate the time taken by Raja and Baja to complete the 42 units of work together
- The combined efficiency of Raja and Baja working together is:
Combined Efficiency=Efficiency of Raja+Efficiency of Baja=3+4=7 units/day
- The time taken to complete the 42 units of work is:
Time=Remaining WorkCombined Efficiency=427=6 days

Step 6: Conclusion
- Since they worked together for 6 days before Baja left, the answer is:
Baja left after 6 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?

    A3
    B5
    C7
    D9
  • Question 2 - Select One

    A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?

    A1425 days
    B9 days
    C8 days
    D359 days