A and B , working together, can complete a work in 16 days, C and A together can complete it in 32 days and C and B together can complete it in 24 days. They worked together for 12 days. In how many days will C can complete the remaining work ? /
A और B एक साथ कार्य करते हुए किसी कार्य को 16 दिनों में कर सकते हैं, C और A इस कार्य को 32 दिनों में कर सकते हैं और C और A इस कार्य को 32 दिनों में कर सकते हैं | उन्होंने 12 दिनों तक साथ कार्य किया | शेष कार्य समाप्त करने में C को कितने दिन लगेंगे ?
40
36
45
32
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information given.
Step 1: Determine the efficiencies of A, B, and C
1. A and B together can complete the work in 16 days.
- Work done in 1 day by A and B = 116 of the work.
- Efficiency of A + B = 6 units (since we will take LCM as 96).
2. C and A together can complete the work in 32 days.
- Work done in 1 day by C and A = 132 of the work.
- Efficiency of C + A = 3 units (since we will take LCM as 96).
3. C and B together can complete the work in 24 days.
- Work done in 1 day by C and B = 124 of the work.
- Efficiency of C + B = 4 units (since we will take LCM as 96).
Step 2: Set up equations
From the above efficiencies, we can set up the following equations:
1. A+B=6 (from A and B)
2. C+A=3 (from C and A)
3. C+B=4 (from C and B)
Step 3: Solve for individual efficiencies
To find the individual efficiencies of A, B, and C, we can manipulate the equations:
1. From equation 1, we can express B=6−A.
2. Substitute B in equation 3:
- C+(6−A)=4
- C+6−A=4
- C−A=−2 → C=A−2 (Equation 4)
3. Substitute C in equation 2:
- (A−2)+A=3
- 2A−2=3
- 2A=5
- A=2.5
4. Now substitute A back to find B and C:
- B=6−2.5=3.5
- C=2.5−2=0.5
Step 4: Calculate total work done in 12 days
Now we know the efficiencies:
- A = 2.5 units/day
- B = 3.5 units/day
- C = 0.5 units/day
The total efficiency of A, B, and C together:
- Total efficiency = A+B+C=2.5+3.5+0.5=6.5 units/day.
In 12 days, the total work done:
- Work done = 6.5×12=78 units.
Step 5: Calculate remaining work
Total work = 96 units (as per LCM).
Remaining work = Total work - Work done = 96−78=18 units.
Step 6: Calculate time taken by C to complete remaining work
C's efficiency = 0.5 units/day.
Time taken by C to complete remaining work = 180.5=36 days.
Final Answer
C will take 36 days to complete the remaining work.
---
1. A and B together can complete the work in 16 days.
- Work done in 1 day by A and B = 116 of the work.
- Efficiency of A + B = 6 units (since we will take LCM as 96).
- Work done in 1 day by C and A = 132 of the work.
- Efficiency of C + A = 3 units (since we will take LCM as 96).
- Work done in 1 day by C and B = 124 of the work.
- Efficiency of C + B = 4 units (since we will take LCM as 96).
From the above efficiencies, we can set up the following equations:
1. A+B=6 (from A and B)
2. C+A=3 (from C and A)
3. C+B=4 (from C and B)
To find the individual efficiencies of A, B, and C, we can manipulate the equations:
1. From equation 1, we can express B=6−A.
2. Substitute B in equation 3:
- C+(6−A)=4
- C+6−A=4
- C−A=−2 → C=A−2 (Equation 4)
- (A−2)+A=3
- 2A−2=3
- 2A=5
- A=2.5
- B=6−2.5=3.5
- C=2.5−2=0.5
Now we know the efficiencies:
- A = 2.5 units/day
- B = 3.5 units/day
- C = 0.5 units/day
- Total efficiency = A+B+C=2.5+3.5+0.5=6.5 units/day.
- Work done = 6.5×12=78 units.
Total work = 96 units (as per LCM).
Remaining work = Total work - Work done = 96−78=18 units.
C's efficiency = 0.5 units/day.
Time taken by C to complete remaining work = 180.5=36 days.
C will take 36 days to complete the remaining work.
Topper's Solved these Questions
Similar Questions
A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
View Solution
Knowledge Check
A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
A40B36C45D32A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
A12013 daysB48013 daysC24013 daysD96013 daysA and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
A80 daysB100 daysC120 daysD150 days
A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?
View SolutionA and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 days
View SolutionA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View Solution