Doubtnut Promotions Sticky

To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को करने के लिए, X और Y की कार्य क्षमताओं का अनुपात 5: 4 है | एक साथ कार्य करते हुए वे इस कार्य को 10 दिनों में समाप्त कर सकते हैं | Y अकेले कार्य शुरू करता है और 5 दिनों के बाद छोड़ देता है | X अकेले शेष कार्य कितने दिनों में पूरा करेगा ?

A

14 days

B

12 days

C

15 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the combined efficiency of X and Y
The ratio of the efficiencies of X and Y is given as 5:4. This means if we let the efficiency of X be 5 units of work per day, then the efficiency of Y will be 4 units of work per day.

Combined efficiency of X and Y:
Efficiency of X+Efficiency of Y=5+4=9 units of work per day

Step 2: Calculate the total work
We know that X and Y together can complete the work in 10 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=9 units/day×10 days=90 units

Step 3: Calculate the work done by Y in 5 days
Y starts the work and works for 5 days. The work done by Y in those 5 days is:
Work done by Y=Efficiency of Y×Time=4 units/day×5 days=20 units

Step 4: Calculate the remaining work
After Y has worked for 5 days, the remaining work can be calculated as:
Remaining Work=Total WorkWork done by Y=90 units20 units=70 units

Step 5: Calculate the time taken by X to complete the remaining work
Now, X will complete the remaining work alone. The time taken by X to complete the remaining 70 units of work is:
Time taken by X=Remaining WorkEfficiency of X=70 units5 units/day=14 days

Final Answer
X will complete the remaining work in 14 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:

    A60 days
    B57 days
    C54 days
    D50 days
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • Question 3 - Select One

    The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :

    A54 days
    B45 days
    C60 days
    D85 days